Articles from Ontario

Wind farm equipment removed

Cancelling 758 renewable energy contracts—including Otter Creek– was one of the first moves of the newly elected Progressive Conservative party after they were elected in the spring of 2018. The project was expected to be built and commissioned by the end of 2019.  
14 Feb 2019

Wind energy may be green, but the water in Chatham-Kent is brown

Residents realized their worst fears as the project began the construction phase last summer. Nineteen wells began to experience sediment problems, Jakubec says — nearly a third of the 64 wells that the group members had tested at their own expense. Bill Clarke, a hydrogeologist for Water Wells First who gathered and analyzed the samples, says follow-up testing showed the affected wells experienced changes in water turbidity, amount of particles, colour, and rate of flow.
12 Feb 2019

North Stormont citizens lose wind turbine appeal

In a decision dated late last week, the Ontario's Environmental Review Tribunal said the group's evidence was not strong enough. "We were not surprised by the tribunal's ruling, but we were disappointed by the outcome," said Margaret Benke, who lives near the wind farm site and was involved in organizing the appeal. ...Benke said the group is considering a lawsuit, though it may be too costly.
9 Jan 2019

Building wind turbines where they’re not wanted brings down property values

This study also addresses underlying reasons for the lack of consensus across related studies in other jurisdictions. There are a number of potential contributing factors, including the possibility that differences in attitudes toward wind energy may influence the likelihood of property value impacts. Areas with greater opposition to wind energy development may be more likely to experience negative impacts on property values. I examined the degree to which differences in attitudes influenced property values in Ontario.
8 Jan 2019

Ontario Scraps the Green Energy Act

"The Green Energy Repeal Act eliminates a piece of legislation that introduced disastrous changes to Ontario's energy system that led to rising electricity rates for families and businesses," said Minister of Energy, Northern Development and Mines, Greg Rickford. "By repealing this act, we're restoring planning decisions to municipalities that were stripped by previous government and ensuring local voices have the final say on energy projects in their communities."
8 Dec 2018

Ontario plans Green Energy Act repeal

Infrastructure minister Monte McNaughton said: "Well-connected energy insiders made fortunes putting up wind farms and solar panels that gouge hydro consumers in order to generate electricity that Ontario doesn’t need. "Today, we are proud to say that the party with taxpayers’ money is over."
21 Sep 2018

Rex Murphy: The Green Energy Act is dead. Let that be a warning to green politicians

The Green Energy and Green Economy Act, which the Ford government announced Thursday it would officially cancel, was one of the most monumental government follies of our time. It was a hydra-headed monster of regulations and fiat that bludgeoned Ontario’s rural communities, stripped Ontario’s municipalities of every right to the slightest participation in their own planning, placed a darkling pall over the manufacturing industry, and imposed the highest electricity costs in all North America on some of Ontario’s lowest-income citizens.
21 Sep 2018

Government still promising health-hazard investigation

Water Wells First, a grassroots group, began raising concerns two years ago about the potential impact the construction of the North Kent Wind farm would have on water wells due to Kettle Point black shale geology and the shallow aquifer in the area. Since then, more than 20 water wells have reported significant amounts of sediments that have clogged up the flow of water during construction and after operation of the wind farm began.
4 Sep 2018

Wind farm killed by new government following legal battle

“It is a clear example of sovereign risk. It is certainly not unique, but it is a reminder of how the government can pass legislation that deprives a party of contractual rights or remedies,” says O’Neill. “You are not dealing with a private counter-party. You are dealing with an entity that has statute-making power.” 
13 Aug 2018

Contractors for Amherst Island wind turbine project owed millions

Rob Scoffield, the managing director of QCE Canada, a wind turbine construction company claims his company is owed about $10 million for work over the last year on the project "Basically this whole thing stinks," he said in an interview. ...Algonquin Power and Pennecon had fallen behind on the project and have had cost overruns of about $90 million. It's a $400- to $450-million project now, he said.
28 Jul 2018

Massive Ontario forest fire sparked by wind farm construction during extreme fire ban, workers allege

Ontario's Ministry of Natural Resources and Forestry is investigating whether construction crews building a major wind-turbine project on the eastern shores of Georgian Bay amidst tinder-dry conditions caused a forest fire that is now devouring more than 5,600 hectares of land. ..."They were still blasting every day, sometimes two or three shots a day," one worker said, despite the extreme fire-hazard conditions. "We've had fires start off beside blasting mats, but it still went on every day.
24 Jul 2018

Trudeau’s tough climate policies face a mounting backlash

The growing backlash to Canada’s climate push reflects a number of changes, experts say. Those include widespread anger in Ontario as electricity prices soared in recent years, driven in part by a shift to renewables; worries about the economy amid a brewing trade war; and the rollback of U.S. climate policies under President Donald Trump, which could draw energy investment away from Canada.
20 Jul 2018

Ontario government axes wind projects

Citing savings to ratepayers, Ontario has announced the cancellation of 758 renewable energy contracts, including several wind energy projects. ...All of the cancelled projects have not reached project development milestones; terminating the projects at this early stage will maximize benefits for ratepayers, the government claims.
17 Jul 2018

http://www.windaction.org/posts?location=Ontario&type=Article
back to top