Articles from Oklahoma

The public addresses regulators over Public Service Co. of Oklahoma's wind farm plan

Nearly every seat was filled Thursday at the Oklahoma Corporation Commission's main courtroom as the agency took public comment on a cause filed by Public Service Co. of Oklahoma. The utility seeks preapproval to recover its costs associated to a large wind power and transmission project that will provide renewable energy to both its customers and those of a sister utility. 
5 Jan 2018

Environmentalists blast TVA for killing major wind project

The nation's biggest wind generator, NextEra Energy Resources, has bought the Oklahoma portion of the proposed 700-mile-long Plains and Eastern Line to serve Oklahoma and Midwest customers. But for now, plans to bring wind energy from the windy areas of Oklahoma and Texas into the less-windy Tennessee Valley and Southeastern part of the United States are stalled and unlikely to be resurrected for years.
31 Dec 2017

Corporation Commission chooses to ‘do nothing’ on Wind Catcher appeal

“We just hate the position that we are in. We hate that this project was commenced. We hate that there wasn’t competitive bidding, which is required by the rule, one or the other,” Hunter said near the end of his argument. “We hate that eight months elapsed from the [inception] of the project until the application was filed, so we’re all being put in a position of being leveraged. If these things aren’t approved in multiple states, this project isn’t going to go forward.”
21 Dec 2017

Route of 350-mile Wind Catcher power line concerns Woodward County ranchers as sinkholes spread

“There is no way any power transmission line coming out of the Panhandle is going to miss important prairie chicken habitat because the best prairie chicken habitat in Oklahoma is in Beaver County. There’s just no way to miss it,” she said. “It is an issue, but right now our main concerns are the bats and destroying their (hibernation area), the erosion it could cause and the idea of building a power line across this area with all these sinkholes.”
30 Nov 2017

10th Circuit Court declines to rehear Wind Farm case

In a unanimous decision issued in mid-September, a three-judge panel reversed and remanded a September 2015 summary judgment from the Northern District Court of Oklahoma that allowed Osage Wind to conduct excavation work in order to set up 84 wind turbines across 8,400 acres without a mining permit from the Bureau of Indian Affairs or approval from the Osage Minerals Council.
18 Oct 2017

Air Force bases must have areas protected from wind farm intrusion

Speaking Tuesday, Lt. Gen. Lee Levy, commander of Air Force Sustainment Center, Air Force Materiel Command, Tinker, said wind turbines that rise hundreds of feet into the sky are encroaching on the flight corridors. Some of those turbines now are in the paths of low-flying planes, requiring the Air Force to abandon routes or take other evasive action.
12 Oct 2017

Osage Nation wins wind farm fight

The Denver Federal Appeals court, in a unanimous decision overturned a lower court ruling and said Enel Green, the owner of Osage Wind, had to obtain a mining permit in the construction of its wind farm in western Osage County, land controlled by the Osage Nation.
27 Sep 2017

PSO Wind Catcher case should proceed, regulatory judge says

Without comment, Corporation Commission Administrative Law Judge Mary Candler denied the attorney general's motion in a hearing Thursday morning. However, Candler approved another motion to have PSO pay for witness fees and other case costs for the attorney general's office, which represents consumers in utility cases.
25 Aug 2017

Oklahoma AG, PSO argue over case for $4.5 billion Wind Catcher project

In Friday's hearing, Assistant Attorney General Dara Derryberry said commission rules only allow preapproval for generation capacity. ...PSO couldn't ask for a waiver of competitive bidding rules because construction has already started on the wind farm. Commission rules allow a pre-construction review as an alternative to competitive bidding, but PSO didn't ask for that either, she said.
19 Aug 2017

Oklahoma AG seeks dismissal of PSO Wind Catcher case

The motion, filed late Friday by Attorney General Mike Hunter's public utility division, said if the commission doesn't dismiss the case, it should make PSO pay for the attorney general's costs to represent Oklahoma consumers in the case. "...PSO's customers are at risk to bear the $1.36 billion cost of the Wind Catcher project if the commission grants PSO's requested relief." 
15 Aug 2017

http://www.windaction.org/posts?location=Oklahoma&type=Article
back to top