Library filed under General from Oklahoma

The public addresses regulators over Public Service Co. of Oklahoma's wind farm plan

Nearly every seat was filled Thursday at the Oklahoma Corporation Commission's main courtroom as the agency took public comment on a cause filed by Public Service Co. of Oklahoma. The utility seeks preapproval to recover its costs associated to a large wind power and transmission project that will provide renewable energy to both its customers and those of a sister utility. 
5 Jan 2018

Corporation Commission chooses to ‘do nothing’ on Wind Catcher appeal

“We just hate the position that we are in. We hate that this project was commenced. We hate that there wasn’t competitive bidding, which is required by the rule, one or the other,” Hunter said near the end of his argument. “We hate that eight months elapsed from the [inception] of the project until the application was filed, so we’re all being put in a position of being leveraged. If these things aren’t approved in multiple states, this project isn’t going to go forward.”
21 Dec 2017

PSO Wind Catcher case should proceed, regulatory judge says

Without comment, Corporation Commission Administrative Law Judge Mary Candler denied the attorney general's motion in a hearing Thursday morning. However, Candler approved another motion to have PSO pay for witness fees and other case costs for the attorney general's office, which represents consumers in utility cases.
25 Aug 2017

Oklahoma AG, PSO argue over case for $4.5 billion Wind Catcher project

In Friday's hearing, Assistant Attorney General Dara Derryberry said commission rules only allow preapproval for generation capacity. ...PSO couldn't ask for a waiver of competitive bidding rules because construction has already started on the wind farm. Commission rules allow a pre-construction review as an alternative to competitive bidding, but PSO didn't ask for that either, she said.
19 Aug 2017

Oklahoma AG seeks dismissal of PSO Wind Catcher case

The motion, filed late Friday by Attorney General Mike Hunter's public utility division, said if the commission doesn't dismiss the case, it should make PSO pay for the attorney general's costs to represent Oklahoma consumers in the case. "...PSO's customers are at risk to bear the $1.36 billion cost of the Wind Catcher project if the commission grants PSO's requested relief." 
15 Aug 2017

Researchers found they could hack entire wind farms

On a sunny day last summer, in the middle of a vast cornfield somewhere in the large, windy middle of America, two researchers from the University of Tulsa stepped into an oven-hot, elevator-sized chamber within the base of a 300-foot-tall wind turbine. They’d picked the simple pin-and-tumbler lock on the turbine’s metal door in less than a minute and opened the unsecured server closet inside.
29 Jun 2017

Kingfisher Wind: No completion by end-of-year deadline

An Oklahoma wind project in Canadian and Kingfisher County will not be completed by its deadline, according to an Apex Clean Line Energy official. Apex spokeswoman Davhi Wilson said construction with the Kingfisher Wind facility is ongoing, even though it was scheduled to be completed before the end of 2015.
28 Dec 2015

Osage County plans advanced for 2nd wind farm

Tradewind is prepared to proceed with construction of Mustang Run even though an Oklahoma Supreme Court ruling is still pending. Completion of the project in 2016 would allow it to receive some significant state tax credits that are scheduled to expire at the end of next year.
19 Jul 2015

http://www.windaction.org/posts?location=Oklahoma&topic=General
back to top