Camp Perry Wind Complaint

Campperrycomplaintasfiled-1_thumb Two leading bird conservation groups, American Bird Conservancy (ABC) and Black Swamp Bird Observatory (BSBO), have filed a lawsuit against the Ohio Air National Guard (ANG) over its plans to build and operate a wind turbine at its Camp Perry facility. Located in Port Clinton, Ohio, on the shore of Lake Erie, Camp Perry lies in a major bird migration corridor, close to numerous Bald Eagle nests, and is likely to kill species protected under the Endangered Species Act such as Kirtland's Warbler and Piping Plover. The complaint can be accessed by clicking the links on this page. A portion of the complaint is provided below.
27 Mar 2017

ABC brief supporting disclosure of bird-bat mortality: Blue Creek Wind facility

Brief_thumb This brief, filed before the Ohio Court of Common Pleas in Franklin County, Ohio, responds to Iberdrola's (Avangrid Renewables) action to stop any public disclose of bird/bat mortality data at its Blue Creek wind facility. Iberdrola has argued that the number of birds and bats killed by its turbines is a “trade secret” protected under Ohio law. The introduction and summary of arguments for why Iberdrola's claims are not supported by Ohio law are provided below. The full brief can be accessed by clicking the links on this page. The original complaint can be found here. 
7 Mar 2017

South Central Board of Education: Letter opposes wind project

Skmbt_55214090911000_thumb This letter, signed by each member of the South Central Board of Education, was submitted to the Ohio Power Siting Board in reference to the proposed Greenwich wind energy facility to be located in Huron County, Ohio. The 60 MW project would span approximately 4,600 acres and consist of up to 25 turbines, each at 2.4 MW. The project was approved by the Ohio Power Siting Board in August 2014. The content of the letter is provided below. The actual letter can be downloaded by clicking the link on this page.
22 Aug 2014

Supreme Court of Ohio order on Application of Buckeye Wind, L.L.C.

2012-ohio-878_thumb The Supreme Court of Ohio upheld an order issued by the state’s Power Siting Board approving the application of Buckeye Wind LLC to construct and operate a large-scale “wind farm” in Champaign County. The court’s 4-3 opinion authored by Justice Judith Ann Lanzinger includes dissenting opinions by two justices. The dissenting opinions provide important insight into the problems with the State's approval of the project. Those opinions are provided below. The full order can be accessed by clicking on the links at the bottom of this page.
5 Mar 2012

Report: Champaign County, OH wind turbine study group

Wtgsreport_thumb This report is a culmination of eight months of effort by the Champaign County (Ohio) Wind Turbine Study Group (“WTSG”). It contains the results of the research and critical analysis compiled by the group regarding fourteen readily identifiable issues associated with wind energy development. The letter introducing the report is listed below along with the report's table of contents. The full document can be downloaded by clicking on the link at the bottom of the page.