Library from North Dakota

PSC’s Brady Wind II hearing lasts more than 10 hours

No one could deny the addition of jobs wasn't a positive. However, residents were able to voice their concerns on a number of other issues, including the noise of the blades, the aesthetic of the towers, the damage to the soil from the concrete foundations, the impact on wildlife and the increase in electric costs, among other things.
8 Jun 2016

Brady II goes before PSC Tuesday

The Hettinger County Commission approved the proposed wind farm on April 8. Now the weight of the decision rests on the PSC. The first phase of the project had much opposition along with proponent comments at a March PSC hearing.
7 Jun 2016

PSC inches closer to Brady Wind decision

A work session followed the special meeting as the PSC continued discussing the 15-hour meeting so they could move closer to reaching a conclusion as to whether the proposed wind farm is in compliance with laws and regulations. The public has 10 days to make comment or cross-examine new exhibits admitted to the record Friday. 
28 May 2016

Another wind farm proposed for Stark and Hettinger Counties

The first wind farm hasn’t yet been built – but the developers of the Brady wind farm in Stark and Hettinger counties have proposed a second wind farm for that same area. ...The North Dakota Public Service Commission is requiring the developer to submit the proposed locations for the wind turbines at least 30 days before the public hearing.
21 Apr 2016

Hettinger County approves wind farm permit

Brady Wind II is a separate project and a separate power-purchase agreement than the Brady Wind I project in southern Stark County. The state Public Service Commission heard 15 hours of testimony March 30 regarding that project and may not make its final decision to either approve or deny it until late May. Combined, the two phases of the Brady Wind Energy Center would put 159 turbines generating about 300 megawatts of power in a rural area.
9 Apr 2016

Citizens' group disputes wind farm location

"Of the 40 landowners who agreed to have turbines, half are residents and half are absentee owners,” said Reichert, adding that the group is holding out for deeper setbacks, so turbines would have to be located 2,000 feet from a property line, not from a residence. “Otherwise, that residence is being used to make up the setback and we think that’s easement trespass,” Reichert said.
8 Mar 2016

Public hearing on Brady Wind farm delayed

The hearing on the wind farm is now scheduled for 8 a.m. March 30 at Dickinson City Hall, while a hearing on the transmission line will be held at 5 p.m. that same day. The 87-turbine, 150-megawatt wind farm would stretch across the south side of the county between Dickinson and New England.
26 Feb 2016

Wind farm approved: Stark County approves 87-turbine wind farm despite division among officials, residents

A muffled groan could be heard from members of the audience as Stark County Commissioner Jay Elkin voted “aye,” the third and deciding vote that approved a conditional-use permit for a wind farm to be erected in southern Stark County. Both the Stark County Commission and Planning and Zoning Board convened at respective special and regular meetings Tuesday morning at Stark County Courthouse to vote on the Brady Wind Energy Center proposed by Florida-based NextEra Energy Resources.
23 Dec 2015

Williams County wind farm project approved

The project originally had been located 2 miles north of Tioga. It was moved to 4 miles away after city officials voiced concerns about the future growth of the city to the north being impacted by a wind farm that close. Tioga City Commission President Drake McClelland said he appreciated the project being moved further north but expressed concern it could still impact future city growth to the north, which is where single-family housing would work best.
3 Dec 2015

Proposed North Dakota wind farm’s impact on bald eagles needs more study, FWS official says

Rolette Power was first informed of bald eagles in the area in 2013 and initially made “a good effort” to work with the FWS to address the issue. But [the service] hasn’t heard from them since December 2014 and they haven’t provided an eagle use study, which the service recommends should take two years to determine where the eagles spend their time.
18 Nov 2015

http://www.windaction.org/posts?location=North+Dakota&p=4
back to top