Library from Minnesota

Developers ditch disputed SE Minn. wind farm project

Developers have formally abandoned their plans to build a $180 million wind farm in southeastern Minnesota that drew strong citizen opposition because of the threat it posed to eagles and bats, according to a regulatory filing Tuesday. New Era Wind Farm LLC told the Minnesota Public Utilities Commission in a letter dated Sept. 6 that it "no longer intends to develop a wind energy project in Goodhue County" and asked the commission to close all pending matters related to the project. The U.S. Fish and Wildlife Service had estimated that New Era's wind turbines could kill as many as eight to 15 bald eagles per year in a worst-case scenario. The company's estimate was one eagle annually. Duration: 1 minute 50 seconds
20 Sep 2013

New Era comes to an end

Opposition to the wind farm from citizens groups centered largely on impacts to wildlife, including eagle and bat populations. The PUC rejected New Era's plan to protect the animals, causing a delay in construction.
18 Sep 2013

Troubled wind project target of FBI scrutiny, industry criticism

Local critics of the $180 million wind project, representing opposition groups Goodhue Wind Truth and the Coalition for Sensible Siting, say they spent a January morning in St. Paul detailing their concerns to two FBI investigators. Developers have spent more than $15 million seeking state permits, according to a filing at the PUC, while local opposition has spent six figures in the protracted legal battle.
31 Aug 2013

Divisive Goodhue County wind debate nears end

The controversy often pitted neighbor against neighbor, but the battle appears near an end. New Era recently missed two deadlines with the Minnesota Public Utilities Commission, which is expected to hold permit revocation hearings in October or November. That could put an end to an unprecedented five-year battle that's included five lawsuits. "It's like tearing a scab off in our community."
31 Aug 2013

Minnesota PUC order on New Era (AWA Goodhue) Wind

Mnpuc-ordernewerawind_thumb The wind project formerly known as AWA Goodhue Wind received this final blow by the Minnesota PUC refusing any further extensions of the permit. The utility giant, XCEL has also canceled the power purchase agreement for the energy. Excerpts of the order are provided below. The full order can be accessed by clicking on the link at the bottom of this page.
26 Jul 2013

Repair work on VA hospital's turbine project hits a snag

The mounting frustration of St. Cloud VA officials was evident Wednesday at the turbine site. A crew with a massive crane couldn't work on the turbine due to high winds that day. And a hulking, blue replacement gearbox sat untouched after VA officials had just learned it had been damaged in shipment. It wasn't an unprecedented development. The original construction of the turbine also was delayed after its blades were damaged in shipment.
13 Jul 2013

Minnesota regulators have pulled the plug on a Goodhue County wind farm proposal

The developer, New Era Wind Farm, could try to revive the $180 million project, its attorney said. But Thursday, PUC commissioners voted unanimously not to extend the company's legal authority to build the 48 wind towers in the county. The clearly frustrated commissioners cited ongoing questions about the company's ownership, the status of its contract with Xcel, and its failure to come up with a plan to protect birds and bats from turbine blades.
20 Jun 2013

Xcel wants out of Goodhue wind deal

Jim Alders, Xcel's directory of regulatory affairs, said Wednesday that Xcel had been committed to the agreement but informed New Era in December that it needed to resolve outstanding issues with the project by early May. "We gave them [New Era] until now to cure those problems and they have not," he said. "We finally reached the point where the contract gives us the right to terminate."
29 May 2013

http://www.windaction.org/posts?location=Minnesota&p=6
back to top