Articles filed under General from Minnesota

Juhl Energy files SEC paperwork to suspend reporting obligations

Citing significant costs but limited benefit, Pipestone, Minn.-based Juhl Energy filed with the Securities and Exchange Commission (SEC) to de-register its common stock and suspend its reporting obligations. The company says it will still trade publicly but via OTC Pink - an exchange that does not have any reporting requirements. In Wall Street parlance, so-called "pink sheets" get their name from an earlier paper-based system that printed on pink paper.
25 Sep 2015

Sibley Wind Substation, Comfrey Wind Energy permits revoked

Both Sibley Wind Substation, planned for southwest of Winthrop, and Comfrey Wind Energy, planned for west of Comfrey, saw their licenses from the Public Utilities Commission revoked. ...Comfrey Wind had been granted two extensions and sought to be covered by the federal Production Tax Credit, so began some construction before the end of 2014. But the state Department of Commerce said construction came before some compliance filings with the commission.
1 Sep 2015

Sibley Wind project permits to be pulled

Sibley-wind-20157-112929-01_thumb Sibley Wind Substation, which had begun utility work for its 10-turbine wind power project, is now asking to withdraw its permits from county and state governments. The memo submitted to the MN PUC can be accessed by clicking the link on this page.
2 Aug 2015

Wind farms once used for U research may close

Shortly after the research concluded, investors learned about a Federal Energy Regulatory Commission policy change from 2006 that they hadn’t been following. It required power purchase agreement farms that produce less than 20 megawatts of energy to fill out paperwork that certified them to do so. But when the farms began 13 years ago, this paperwork was optional. After eight years of unfiled paperwork, the farms were hit with the civil liability and subsequently had to file for bankruptcy.
29 Jan 2015

Legislator wants to revoke permit on unpopular wind project

“This has been going on, just hanging there, sitting there,” said Barb Wenninger, a Cornish Township resident and longtime opponent of the Sibley Wind Substation turbines. “We seem to have shown violations of their permit, and no action has been taken. That’s what it seems to us, like nothing is being resolved.”
17 Oct 2014

Leaders, VA wind turbine needs attention

Building — and trying to fix — the turbine already has cost taxpayers about $2.3 million, 99 percent of which the VA has paid to the private contractors responsible. And please note that does not include more than $325,000 the VA has not accrued in energy savings since the turbine went online in April 2011. In other words, this project alone has cost taxpayers more than $2.6 million. It still does not work, nor have any funds expended been recovered.
7 Sep 2014

You don't own the wind

The plaintiffs claim this ordinance is pre-empted by Minnesota Statute § 216F.02(b), "which prohibits local governments from enacting complete bans on businesses and homeowners using SWECS [small wind energy conversion systems] to generate electricity."
9 May 2014

Where is the answer for VA turbine's financial drain?

What was supposed to provide up to 15 percent of the power to the St. Cloud VA Health Care System has turned into a black eye in the sky. ...Nearly $2.3 million went blowing in the wind, and there seems to be no end in sight to needed repairs. It’s also unclear whether the VA will be compensated for lost savings or if the turbine will ever work properly.
8 Mar 2014

St. Cloud VA's wind turbine has yet to live up to expectations

Almost three years after it was built, a wind turbine at the St. Cloud VA Health Care System has become a towering boondoggle. The VA system paid about 99 percent of the $2.3 million cost for the turbine. All that has bought is a turbine that supplied a tiny fraction of the power it was expected to generate. Since August 2012, the turbine has supplied no power at all. ...“You fix one thing and something else pops up. It’s extraordinarily unreliable.”
2 Mar 2014

State approves taller turbines in Pleasant Valley wind project

The PUC approved the initial site permit for a 301 megawatt project in 2010, but the amended request reduces the nameplate capacity to 200 megawatts. Additionally, the PUC's recent decision allows Pleasant Valley to switch from a combination of 1.5 MW and 2.3 MW General Electric turbines to a uniform layout of 2.0 MW Vestas, which are 328 feet tall with a rotor diameter of 328 feet. The GE turbines had the same rotor diameter, but the towers stood 262 feet tall.
15 Feb 2014

Plug pulled on EcoHarmony wind project in Fillmore County

The EcoHarmony wind project received its permits in February 2010 ...the 280-megawatt project would have been the largest wind development in state history. However, the project layout was overhauled in early 2013, shrinking to 116 megawatts. The company's plans changed again this fall when Gamesa notified local project participants that the project was dead.
26 Dec 2013

For Minnesota utility, wind backed by hydro is ‘holy grail’

In northern Minnesota, an electric utility is proposing a 500 kV, cross-border transmission line that would let it tap Canadian hydropower under a similar arrangement. Minnesota Power says the Great Northern Transmission Line would allow it to balance intermittent power from its North Dakota wind farms with dispatchable power from Manitoba hydro facilities.
3 Dec 2013

Another local wind project bites the dust

"...I regret to have to inform you that National Wind/Trishe Wind Energy has made the difficult decision to terminate the High Country Energy project," wrote National Wind and Trishe Wind Energy President Vivek Mittal. "Despite our best efforts, we have not been able to sign on enough contiguous acres necessary for the planned 150 (megawatt) project or to win the broad community support essential to bringing a wind project to successful commercial operation."
25 Oct 2013

http://www.windaction.org/posts?location=Minnesota&p=2&topic=General&type=Article
back to top