Library from Michigan

Turbines still, but progress is being made

While it’s still uncertain when the turbine blades will start spinning again at Elkton-Pigeon-Bay Port Laker Elementary, there has been some positive movement on the issue regarding DTE Energy requirements that led to the turbines being turned off last week.
30 Sep 2006

Second wind farm project halted

The wind has been taken right out of a second wind energy project in the Thumb Area. Last month, Michigan’s first wind farm near Ubly was put on hold until next year. Now a smaller wind energy project in the Laker School District near Pigeon has been shut down by DTE Energy. The utility company says safety is the reason, but others disagree.
26 Sep 2006

Thumb windmills idled after DTE Energy raises concerns

PIGEON - Three windmills erected at a Thumb elementary school have been shut down, and supporters says it’s because DTE Energy doesn’t want to see wind power succeed here. A DTE spokesman says the utility supports renewable energy, but there were ‘’safety and reliability'’ concerns about allowing the school windmills to continue supplying power to the electrical grid. It’s the second time this year that people in the Thumb have blamed DTE for delays to wind power projects.
25 Sep 2006

DTE orders Lakers to shut down turbines

PIGEON — Just as the three wind turbines by Elkton-Pigeon-Bay Port Laker Elementary School only recently started spinning after a long wait, those involved with the turbine project are facing difficulties with DTE Energy — and it’s making their heads spin. “DTE personnel have demanded that these turbines be shut down immediately and not restarted until (a) seven-week study is completed, the school district pays for the upgrading of DTE equipment, and that equipment is installed by DTE personnel,” said Laker Interim Superintendent Bob Drury in a press release. Les Singer, DTE Energy spokesman, said there are requirements for any customer that interconnects with the company’s system to ensure that their equipment can safely and compatibly work with the system.
21 Sep 2006

Expert discusses possibility of turbines in area

Earlier this year, the U.S. Department of Energy released $1 million to measure how fast, on average, the wind blows coming off the river. The measurement is part of the Wyandotte Green Windpower on Brownfields Project, an initiative through which wind turbines could be installed on contaminated property.
2 Sep 2006

Wind's potential - Professor studies energy source

Central Michigan University could help create a statewide wind energy movement if a planned research study confirms one professor's suppositions. Associate professor of physics Frederick Phelps plans to conduct a two-year wind study of the central and northern Michigan area at dozens of sites to determine if wind velocities are sufficient to make wind turbines economically feasible.
20 Aug 2006

Red tape delays Ubly wind park

Noble Environmental Power has decided to delay building the first phase of its wind park near Ubly until next year. For almost a year, the company and DTE Energy have been working on an interconnection agreement that would use the utility company's power lines to move energy generated by the park's wind-powered turbines. The agreement, however, has become entangled in red tape involving the Federal Energy Regulatory Commission.
12 Aug 2006

Proposed Golden Township Zoning Ordinance

Golden_township_zoning_ordinance_thumb Please note that anything of lighter color or crossed out is the recommendation from the township attorney. The markup reflects the attorney's view that any environmental clauses can be challenged in the courts and the township should not take on the liability of being an "expert" in intrepreting the studies presented to them by the developer or citizen.
1 Aug 2006

Traverse City (MI)

Bilde_thumb The City of Traverse City installed a wind generator in June 1995 on a hill west of the city. In this photo shot Thursday, July 27, 2006, the unit stands on a 160-foot tower with a blade diameter of 144 feet. The huge wind turbine was the largest in the United States when installed.
27 Jul 2006

Proposed wind farm on hold - Company to wait for township to draft ordinance

CEDAR — Possible plans for a wind farm in Centerville Township are on hold until at least next year while the township drafts a zoning ordinance to regulate commercial windmills. Tim Johnson, township planning commission chairman, said Noble Environmental Power agreed to not submit a formal application until the ordinance — which would apply to wind energy projects proposed by Noble or any other developer — is complete.
27 Jul 2006

Wind-farm project gets caught up in turbulence - Developer scales back plan amid utility concerns

In January, Noble Environmental Power - which operates wind parks in Connecticut and New York and has an office in Bad Axe - said 32 turbines would be up by July. Now, the plan is to build seven, and that must wait until the company and DTE Energy have determined how to move the power they generate to the Thumb's electrical-transmission system. "Once we solve these interconnection issues, we'll proceed with building the wind park" as originally planned, said Noble's Jeanette Haggen, the project's development manager.
25 Jul 2006

AG wants 5¢ off energy bills

Every month, customers of Consumers Energy pay a tad more on their utility bill to subsidize renewable energy in Michigan, and it's an even bet most don't even know it. ...It's only a measly nickel, and for what some believe is a noble cause. But Michigan Attorney General Mike Cox wants to yank the plug.
18 Jun 2006

http://www.windaction.org/posts?location=Michigan&p=63
back to top