Court order: DOE failed to consider environmental impacts on Mexico

Esj_court_ruling_for_bad_27s_msj_1-30-17_thumb This important decision by the U.S. District Court of the Southern District in California found that the Department of Energy failed to follow NEPA when it issued a permit to construct a transmission line that crossed over from Mexico into the United States. The Court order that since the U.S. portion of the Line and the Mexican portion of the Line were literally "two links of a single chain" connecting the Substation to the ESJ Wind Farm, the DOE was required to consider the impacts of the project on Mexico. Portions of the decision are shown below. The full report can be accessed by clicking the document link on this page.
30 Jan 2017