Articles filed under Offshore Wind from Massachusetts

Edgartown, Vineyard Wind double-down

Edgartown conservation agent Jane Varkonda told The Times Edgartown didn’t receive the August 5 superseding order of conditions from the commonwealth in a timely manner. Varkonda said she learned by happenstance the decision had been made during a conversation with a state official. Upon learning Edgartown was without the decision, the official sent it.
28 Aug 2019

Troubling questions, concerns raised about off-shore wind farms

Overwhelming, too, for Al Eagles, a lobsterman from Newport, who questioned why the federal government is allowing projects to go forward when so little is known about their effects. “To me, everything you said up here was all unknowns,” Eagles said to Hare. “We could be devastating entire species out there. By the time we realize it, it would be too late.” Lanny Dellinger, also a Newport lobsterman and chair of a board that advises Rhode Island coastal regulators on fishing issues related to offshore wind, said the entire fishing industry is under threat. 
22 Aug 2019

2 views on Vineyard Wind delay

It is furthermore unclear how Secretary Bernhardt could issue a decision on the DEIS, when critical impact categories such as fishing vessel transit, disruption payments, baseline ecological information, radar interference and others are yet to be settled. 
19 Aug 2019

Sources: Vineyard Wind Decision Delayed Until December 2020

Final approval for the Vineyard Wind Project will likely not happen for at least another 18 months, according to information received from multiple sources by The Public’s Radio. This means the country’s first large scale offshore wind farm won’t begin construction in time to take advantage of a lucrative federal tax credit that expires at the end of the year. 
19 Aug 2019

Feds delay environmental statement for offshore wind project

Connie Gillette, chief of public affairs for the Bureau of Ocean Energy Management, said Friday the agency took the action after receiving comments “from stakeholders and cooperating agencies” requesting a more robust cumulative analysis that would include projects that have been awarded power purchase agreements, but may not have submitted construction and operations plans.
10 Aug 2019

Trump stands up for New Bedford fishing community

The Trump administration was unsatisfied with the studies done on how much the wind industry would impact the fishing industry and has ordered an extended review: "An Interior Department review explored how Vineyard Wind may affect other industries and resources, including marine life. But the National Marine Fisheries Service raised concerns it looked too narrowly at potential cumulative effects on fishing, prompting the supplemental review."
9 Aug 2019

Vineyard Wind Races Against the Clock

Beyond the immediate concerns with permitting, Vineyard Wind faces a tangle of logistical challenges and potential investor turmoil if the project continues to see delays. Anthony Logan, an industry expert with the renewables research firm Wood Mackenzie Power, has spent the past six years forecasting the wind energy field. He said that while Vineyard Wind, barring major disaster, remains poised to become the first industrial-scale offshore wind-farm in the U.S., the financial success of the project is dependent on qualifying for a federal tax incentive for wind energy projects, known as the investment tax credit (ITC).
9 Aug 2019

Vineyard Wind receives gubernatorial boost

One section of the proposed cable route passes through the Muskeget Channel about a mile from Chappaquiddick, and therefore falls under the auspices of the Edgartown conservation commission. In a 5-1 vote, the commission denied Vineyard Wind a permit to lay cable in the channel. Vineyard Wind has since appealed to the Massachusetts Department of Environmental Protection. 
31 Jul 2019

R.I. delegation raises concerns with speed of offshore wind review

Vineyard Wind already agreed to a nearly $17 million mitigation package in Rhode Island. But it doesn’t look like that will be enough. The fishing industry still has many issues. For example, the Long Island Commercial Fishing Association is worried about the effect these giant towers could have on boat radar, and the impediments that transmission cables could cause.
30 Jul 2019

First big U.S. offshore wind project hits snag due to fishing-industry concerns

BOEM spokesman Stephen Boutwell said NMFS is required to co-sign the project’s Record of Decision, a formal decision document, for the permit to be issued. The final environmental impact study and record of decision had originally been expected in April but were later delayed to June and then early July. Boutwell said the agency does not “have a date for these publications at this time.”
29 Jul 2019

Fishermen Are At Heart of Delay in Vineyard Wind Project

The National Marine Fisheries Service is refusing to sign off on an environmental impact report originally expected July 7, Reuters said, citing previously unseen federal documents. Fishing industry representatives want proposed wind turbines farther apart than the currently planned 0.75 nautical mile, want the turbines aligned east-west instead of northwest-southeast, and want compensation for any damage to their livelihoods, according to Reuters.
29 Jul 2019

Vineyard Wind dealing with potential setbacks

Vineyard Wind, the company that's planning to build the state's first offshore wind farm, is facing setbacks for the project of 84 turbines in waters near Martha's Vineyard and Nantucket. The Edgartown Conservation Commission voted against approval for transmission cables that Vineyard Wind wants to lay about a mile east of the town. The Federal Bureau of Ocean Energy Management has put off issuing a final environmental impact statement on the wind farm. Sarah Mizes-Tan, a reporter with WGBH’s Cape Cod bureau, spoke with WGBH Radio’s Arun Rath about the wind farm and some of the setbacks. This transcript has been edited for clarity.
14 Jul 2019

Vineyard Wind project lands in rough waters

The clock is ticking. Vineyard Wind’s utility contracts require the first phase to go online by Jan. 15, 2022. The developer has orders with suppliers lined up that could be jeopardized. There’s also some question about a federal tax credit that expires at the end of 2019. Vineyard Wind has apparently qualified, but that status could be in trouble if certain milestones aren’t met. None of Vineyard Wind’s rivals want to see the project collapse.
13 Jul 2019

http://www.windaction.org/posts?location=Massachusetts&topic=Offshore+Wind&type=Article
back to top