Articles filed under Offshore Wind from Massachusetts

5 offshore wind firms agree to standard configuration

The agreement is significant because many Massachusetts politicians, including US Rep. Joe Kennedy III and Sen. Ed Markey, have accused the Bureau of Ocean Energy Management and the Trump administration of playing politics with the process. But the agreement by the five wind farm developers suggests they, and particularly Vineyard Wind, recognized a need to address the consistency of their project designs.
19 Nov 2019

Vineyard wind pushes IRS for subsidy extension on delayed offshore project

“Since the business case is being impacted by external delays, we are requesting an extension from the IRS for the originally planned ITCs of the project,” Torgerson told analysts. “We’re petitioning the IRS to get an extension of that ITC at the 24 percent level…through the 2022 timeframe.” The delay means Vineyard may be able to upgrade to longer rotor blades for its 9.5-megawatt MHI Vestas turbines, Torgerson said — jumping from a 164-meter rotor diameter up to 174 meters. Longer blades mean more electricity can be generated.
1 Nov 2019

Mayflower’s lowest-price offshore wind option selected

Few details about the price or the onshore investment were revealed, but Mayflower said in its original bid that the price would be “the lowest cost offshore wind energy ever in the US.” Mayflower is a joint venture of Shell New Energies and EDP Renewables. ...It appears Mayflower was far and away the easy choice. The state’s press release said the company offered a lower price and greater economic development opportunities than the other two bidders – Vineyard Wind, the company that won the first offshore wind procurement, and Bay State Energy, which lost for the second time.
30 Oct 2019

Vineyard Wind, Edgartown Commission reach settlement

The commission this summer denied the project's plans to bury two transmission cables in Nantucket Sound and Muskeget Channel areas within Edgartown, and the project appealed to the state Department of Environmental Protection (DEP). After the department issued an order of conditions favoring the project, the commission appealed and the settlement was reached before that appeal was fully heard by another wing of the DEP.
2 Oct 2019

Trump aide offers no guidance on Vineyard Wind

“It’s going to take some time, longer than we expected for this project,” said Bennett, who was asked about the agency’s timetable by Attorney General Maura Healey’s chief of staff, Mike Firestone. Bennett was at the Sheraton Boston Hotel taking part in an offshore wind panel at an eastern region meeting of the National Association of Attorneys General.
27 Sep 2019

Edgartown, Vineyard Wind double-down

Edgartown conservation agent Jane Varkonda told The Times Edgartown didn’t receive the August 5 superseding order of conditions from the commonwealth in a timely manner. Varkonda said she learned by happenstance the decision had been made during a conversation with a state official. Upon learning Edgartown was without the decision, the official sent it.
28 Aug 2019

Troubling questions, concerns raised about off-shore wind farms

Overwhelming, too, for Al Eagles, a lobsterman from Newport, who questioned why the federal government is allowing projects to go forward when so little is known about their effects. “To me, everything you said up here was all unknowns,” Eagles said to Hare. “We could be devastating entire species out there. By the time we realize it, it would be too late.” Lanny Dellinger, also a Newport lobsterman and chair of a board that advises Rhode Island coastal regulators on fishing issues related to offshore wind, said the entire fishing industry is under threat. 
22 Aug 2019

2 views on Vineyard Wind delay

It is furthermore unclear how Secretary Bernhardt could issue a decision on the DEIS, when critical impact categories such as fishing vessel transit, disruption payments, baseline ecological information, radar interference and others are yet to be settled. 
19 Aug 2019

Sources: Vineyard Wind Decision Delayed Until December 2020

Final approval for the Vineyard Wind Project will likely not happen for at least another 18 months, according to information received from multiple sources by The Public’s Radio. This means the country’s first large scale offshore wind farm won’t begin construction in time to take advantage of a lucrative federal tax credit that expires at the end of the year. 
19 Aug 2019

Feds delay environmental statement for offshore wind project

Connie Gillette, chief of public affairs for the Bureau of Ocean Energy Management, said Friday the agency took the action after receiving comments “from stakeholders and cooperating agencies” requesting a more robust cumulative analysis that would include projects that have been awarded power purchase agreements, but may not have submitted construction and operations plans.
10 Aug 2019

Trump stands up for New Bedford fishing community

The Trump administration was unsatisfied with the studies done on how much the wind industry would impact the fishing industry and has ordered an extended review: "An Interior Department review explored how Vineyard Wind may affect other industries and resources, including marine life. But the National Marine Fisheries Service raised concerns it looked too narrowly at potential cumulative effects on fishing, prompting the supplemental review."
9 Aug 2019

Vineyard Wind Races Against the Clock

Beyond the immediate concerns with permitting, Vineyard Wind faces a tangle of logistical challenges and potential investor turmoil if the project continues to see delays. Anthony Logan, an industry expert with the renewables research firm Wood Mackenzie Power, has spent the past six years forecasting the wind energy field. He said that while Vineyard Wind, barring major disaster, remains poised to become the first industrial-scale offshore wind-farm in the U.S., the financial success of the project is dependent on qualifying for a federal tax incentive for wind energy projects, known as the investment tax credit (ITC).
9 Aug 2019

Federal agencies, Vineyard Wind at odds over wind farm setup

All three federal agencies that weighed in on Vineyard Wind’s construction and operations plan have coalesced around the east-to-west orientation of the 84 wind turbines. The three agencies are supporting a distance of at least 1 mile between the turbines, which is a marked contrast to the company’s diagonal layout plan with less space between, according to the Times review of 349 public comments on the draft environmental impact statement.
2 Aug 2019

Vineyard Wind receives gubernatorial boost

One section of the proposed cable route passes through the Muskeget Channel about a mile from Chappaquiddick, and therefore falls under the auspices of the Edgartown conservation commission. In a 5-1 vote, the commission denied Vineyard Wind a permit to lay cable in the channel. Vineyard Wind has since appealed to the Massachusetts Department of Environmental Protection. 
31 Jul 2019

R.I. delegation raises concerns with speed of offshore wind review

Vineyard Wind already agreed to a nearly $17 million mitigation package in Rhode Island. But it doesn’t look like that will be enough. The fishing industry still has many issues. For example, the Long Island Commercial Fishing Association is worried about the effect these giant towers could have on boat radar, and the impediments that transmission cables could cause.
30 Jul 2019

http://www.windaction.org/posts?location=Massachusetts&topic=Offshore+Wind&type=Article
back to top