Articles from Massachusetts

State finds flaws In turbine noise study

In reviewing the study, the Massachusetts Department of Environmental Protection found that noise samples were collected at the wrong time of day and that not all the turbines were spinning when the sampling was done. The state also pointed out that some necessary information was missing from the analysis and that the report provided conflicting information relative to the turbines’ exact locations on the site.
6 Sep 2018

Petition mobilizes opponents of proposed Yarmouth power line

Press_release_petitions_presented_to_gov._and_yamouth_bos_08__28_2018_thumb Thousands of visitors and residents have signed a petition opposing an effort by offshore energy company Vineyard Wind to bring a high-wattage transmission cable through Lewis Bay and onshore in Yarmouth. ...A copy was given to Gov. Charlie Baker last week and to the Yarmouth selectmen at their meeting Tuesday, where Chairman Norman Holcomb told residents the board was open to hearing concerns.
29 Aug 2018

Falmouth resident shares lasting turbine troubles

Wind 1 and Wind 2, the two 1.65-megawatt turbines the Town of Falmouth installed on industrial-zoned land between 2009 and 2010, no longer turn or generate electricity. However, Falmouth residents Neil P. Andersen and Elizabeth L. Andersen said they still feel the aftereffects from the turbines and from their legal fight against them.
28 Aug 2018

Neighbors of Plymouth turbines bring health concerns to Bourne board

In a plea for help, a small group of residents came in front of the Bourne Board of Health on Aug. 8 after a Superior Court judge ruled that Bourne officials didn’t have the authority to regulate the construction of the turbines because they were outside of the town’s jurisdiction. ...however, the judge had written that a “Board of Health has broad powers to regulate and prevent nuisances that affect the public health,” adding that it remained to be seen whether the operation of the turbines would be a nuisance affecting the health of Bourne residents.
20 Aug 2018

Conflicted DEP fails to address wind hazards

The DEP can no longer help enforce its own regulations because of its involvement in wind turbine contracts. The Project Regulatory Agreement does not take into consideration public health and safety it has become immoral with despicable inhuman conduct bordering on criminal. We know today the DEP has been aware residents have been living in a toxic environment around the wind turbines.
13 Aug 2018

Buzzards Bay residents raise issue with turbines

Buzzards Bay residents plagued night-and-day by four Future Generation wind turbines operating on Mann cranberry bog in South Plymouth have returned to the Bourne Board of Health seeking intervention and relief. The board, however, says its jurisdiction does not extend across the town line. The board has been legally advised not to consider out-of-town matters already adjudicated by the Barnstable Superior Court.
10 Aug 2018

Bay State Wind alters layout for offshore wind farm, but fisheries call foul

"The fishing industry can only hope that the wind energy developers finally recognize that U.S. fishermen are going to do whatever is necessary to continue to fish where they please for the foreseeable future," Dave Wallace, a Maryland-based consultant for the ocean clam industry, said in an email. "Developers have two choices, a confrontational way, which is time-consuming and expensive, or through the two industries finding common grounds where both can survive and prosper."
7 Aug 2018

Offshore wind prices look competitive

The Vineyard Wind project is split into two, 400-megawatt phases, with the first phase scheduled for completion by January 15, 2022, and the second phase by January 15, 2023. The price for energy and the environmental attributes (called renewable energy credits) starts at 7.4 cents a kilowatt hour in phase one and 6.5 cents a kilowatt hour in phase two. The prices escalate at 2.5 percent a year over the 20-year life of the contract, with an average blended cost of 8.9 cents a kilowatt hour.
2 Aug 2018

Power line plan lights fuse under Yarmouth residents

A plan by offshore power company Vineyard Wind to bring a high-wattage cable through Lewis Bay and onshore in West Yarmouth is energizing residents, who say that no amount of compensation is worth the damage the project could potentially inflict. “This is not about money,” West Yarmouth resident David Bernstein said at Tuesday’s Board of Selectmen meeting, which was devoted primarily to public comment on the project. “I don’t care if Vineyard Wind gives $10 million a year to the town of Yarmouth. If the bay is killed, it is killed.”
19 Jul 2018

Decade in, Savoy wind project reaches pivotal point

On April 5, Building Inspector Phil Delorey rejected the company's application for authorization to begin work to erect five turbines on West Hill, near the Hawley line, on land owned by Harold "Butch" Malloy. Though the project won backing from residents in 2008, sentiment has swung fully against wind energy in Savoy. Residents late last year voided a bylaw allowing commercial wind projects.
18 Jul 2018

Recreational anglers have stake in offshore wind power

Given that everyone from Republican Massachusetts Governor Charlie Baker to Democratic Rhode Island Governor Gina Raimondo to Secretary of the Interior Ryan Zinke have all been vocal in their support for offshore wind power, the question is not if more wind farms will be built, it is if they will be built in a way that works for fishermen — commercial and recreational alike.
30 Jun 2018

http://www.windaction.org/posts?location=Massachusetts&p=4&type=Article
back to top