Library filed under General from Massachusetts

Baker says he’ll sign solar compromise

Associated Industries of Massachusetts issued a statement saying that electric ratepayers will still be on the hook for billions of dollars over a 10-year period to cover the cost of these incentives. John Regan, a lobbyist for the group, wrote a letter to lawmakers saying that the bill is “poorly conceived, it will not lower costs and will not put the commonwealth on a path to a sustainable future.”
8 Apr 2016

Cape Wind appeals permit extension rejection; Wind farm officials say nothing has changed

In its request for an extension of the transmission line approval, Cape Wind said none of the circumstances that led to the original approval has changed. The company said “it is quite feasible” it may be able to begin construction of the wind farm by the extension date of May 1, 2017, but conceded that if there are further delays it may need more extensions.
5 Apr 2016

Time to show wind developers the door

Maine was originally part of Massachusetts, and we act like we are still, but I would admonish Maine residents to rise up and show the wind developers the door. Let them try constructing these useless monstrosities in the Berkshires and see how far they get. I have yet to delineate the total crony corruption that has enabled this industrial wind disaster but here are a few nuggets to chew on.
11 Mar 2016

Saturday meeting to decide turbine permit

The turbines at the town's wastewater treatment facility on Blacksmith Shop Road have been a source of controversy since they were installed. Neighbors have complained about health effects from their operation and have used a number of avenues to try to shut them down, while the town has warned of dire financial consequences should either device be deactivated.
2 Feb 2016

Bourne counsel sets guidelines in turbine case

For the better part of four decades Bourne Town Counsel Robert Troy has had a direct hand in guiding Bourne’s legal affairs and he is not known for tilting at windmills. Now Troy is inching forward with a board of health request that he seek a civil injunction in Barnstable Superior Court to stop construction of the controversial Future Generation Wind turbines in Head of the Bay at South Plymouth.
11 Dec 2015

Denial likely for wind 2 appeals

Members of the Falmouth Zoning Board of Appeals came to a consensus on Monday, November 30, to deny appeals relating to Wind 2, one of two town-owned wind turbines on Blacksmith Shop Road. The board will discuss a draft decision and possibly vote on the matter at its meeting next Thursday, December 10.
4 Dec 2015

Hanover officials optimistic that wind turbine is ‘operating properly now’

“This has been a long and, at times, frustrating journey, but we believe that the route we have taken to work with the surety company has produced the best financial and operational result for the taxpayers in town,” Clarkson said. The turbine cost taxpayers $750,000 to install, and was meant to save the town $50,000 a year on energy costs. As of August, the turbine has saved the town $9,008 since it first went online 2013.
30 Sep 2015

Falmouth selectmen seek approval to resume operation

A day after the Falmouth Board of Selectmen voted in a closed-door session on Monday to shut down Wind 1, one of the town's two wind turbines, while it fights a cease-and-desist order against the device's operation, the board on Tuesday voted to place three warrant articles before the planned Nov. 10 special town meeting. One of the articles would exempt the turbine from zoning requirements retroactively, paving the way for it to be turned back on.
30 Sep 2015

Turbines could cost taxpayers up to $15 million if shut down

Under its court-ordered current half-time operating schedule, the two municipal wind turbines are not generating enough green energy to pay for themselves. And if they are ordered to be shut down, it would mean be a huge financial loss to the town, said Douglas H. Jones, chairman of the board of selectmen. “At this point, I have no idea how we would cover the financial loss. We don’t have the money to cover it."
26 Sep 2015

Bourne officials grapple with Plymouth turbine project

The Future Generation Wind project will be fully constructed in Plymouth, but because of the size of its parts, they'll be unable to be transported on highways, Bourne Board of Selectmen Chair Stephen Mealy said Thursday. The project would require about 24 oversized trucks to carry parts as large as 170 feet long, over 15 feet wide and almost 16 feet tall. ...About 80 feet of guardrail on Head of the Bay Road would need to be removed, Mealy said, so the trucks can navigate the road to the entrance of the farm in Buzzards Bay. 
25 Sep 2015

Delivering wind turbine parts through Bourne is complicated

The proposed delivery of turbine parts has become a high-profile issue for selectmen and was the subject of a special code-enforcement meeting among town inspectors last week. Selectmen at this point do not want to be portrayed as opposed to alternative-energy efforts or local business in general, but members are trying to protect local interests as they relate to infrastructure impacts and early-morning Buzzards Bay motoring disruption.
24 Sep 2015

Falmouth selectmen weigh special town meeting on turbine ruling

The town's wind turbine zoning bylaw was last amended in 2013 when town meeting approved a revision that prohibits turbines with a capacity of more than 250 kilowatts anywhere in town. Both Wind 1 and Wind 2 have capacities of 1.65 megawatts, more than six times what’s permitted by the newer restrictions. The bylaw also limits to 6 decibels the allowable noise levels audible to neighbors from the machines.
23 Sep 2015

Milton wind turbine project is officially dead

Granite Links sued to stop the turbine in 2011, and in 2013 an arbitrator ruled that Milton could build the turbine but could not operate it during golfing hours. The restriction meant the turbine, which had been expected to provide up to $800,000 a year for the town, would no longer be profitable, according to Milton’s planning director, William Clark.
14 Aug 2015

http://www.windaction.org/posts?location=Massachusetts&p=4&topic=General
back to top