Articles from Massachusetts

In Dartmouth, fight looming over long proposed solar farm

McInnes’s Jan. 30, 2020 letter to the Dartmouth Zoning Board of Appeals states that Brady Estates’ time to keep the land for a solar development is up. “Therefore, the Select Board concurrently opposes the present request by Brady Estates to amend the variance decision in order to modify the terms under which it can delay the conveyance of Parcel B,” the letter reads. The Select Board, the letter notes, intends to deliver a demand for execution of the deed “at or before the next hearing date.”
22 Feb 2020

Plymouth board declares turbines a nuisance

The four 500-foot ConEdison Solutions wind turbines were installed in June 2016. They sit close to the Bourne border, but because they are located in Plymouth, it has been difficult for Bourne residents to fight through their own town government. Since their installation, the Buzzards Bay Action Committee, a nonprofit group dedicated to preserve and protect Buzzards Bay, has collected approximately 360 complaints from residents in the area. Complaints include shadow flicker, nausea, vertigo, sleep disturbance, headaches, anxiety and sound disturbances. “We have 360 complaints and they go unanswered,” Plymouth resident Larry McGrath said before the vote was taken. “Nobody does anything to protect us.”
14 Feb 2020

For offshore wind, expect more delays

Federal agencies assessing the environmental impact of Vineyard Wind are now expecting the long-delayed process to wrap up sometime in December, according to a top Baker administration official. ...That timetable is problematic for wind farm developers up and down the coast, but especially for the two companies that have been awarded power purchase contracts by Massachusetts utilities and are eager to begin construction.
3 Feb 2020

Fishermen, wind farm developers at odds

The Responsible Offshore Development Alliance called for the creation of six travel lanes, each one four nautical miles in width, through the entire lease area off the coast of the two states. The offshore wind developers in November had proposed no special travel lanes, choosing instead to let fishermen navigate through turbines set one nautical mile apart traveling north and south and seven-tenths of a nautical mile going diagonally.
7 Jan 2020

5 offshore wind firms agree to standard configuration

The agreement is significant because many Massachusetts politicians, including US Rep. Joe Kennedy III and Sen. Ed Markey, have accused the Bureau of Ocean Energy Management and the Trump administration of playing politics with the process. But the agreement by the five wind farm developers suggests they, and particularly Vineyard Wind, recognized a need to address the consistency of their project designs.
19 Nov 2019

Vineyard wind pushes IRS for subsidy extension on delayed offshore project

“Since the business case is being impacted by external delays, we are requesting an extension from the IRS for the originally planned ITCs of the project,” Torgerson told analysts. “We’re petitioning the IRS to get an extension of that ITC at the 24 percent level…through the 2022 timeframe.” The delay means Vineyard may be able to upgrade to longer rotor blades for its 9.5-megawatt MHI Vestas turbines, Torgerson said — jumping from a 164-meter rotor diameter up to 174 meters. Longer blades mean more electricity can be generated.
1 Nov 2019

Mayflower’s lowest-price offshore wind option selected

Few details about the price or the onshore investment were revealed, but Mayflower said in its original bid that the price would be “the lowest cost offshore wind energy ever in the US.” Mayflower is a joint venture of Shell New Energies and EDP Renewables. ...It appears Mayflower was far and away the easy choice. The state’s press release said the company offered a lower price and greater economic development opportunities than the other two bidders – Vineyard Wind, the company that won the first offshore wind procurement, and Bay State Energy, which lost for the second time.
30 Oct 2019

Vineyard Wind, Edgartown Commission reach settlement

The commission this summer denied the project's plans to bury two transmission cables in Nantucket Sound and Muskeget Channel areas within Edgartown, and the project appealed to the state Department of Environmental Protection (DEP). After the department issued an order of conditions favoring the project, the commission appealed and the settlement was reached before that appeal was fully heard by another wing of the DEP.
2 Oct 2019

Trump aide offers no guidance on Vineyard Wind

“It’s going to take some time, longer than we expected for this project,” said Bennett, who was asked about the agency’s timetable by Attorney General Maura Healey’s chief of staff, Mike Firestone. Bennett was at the Sheraton Boston Hotel taking part in an offshore wind panel at an eastern region meeting of the National Association of Attorneys General.
27 Sep 2019

http://www.windaction.org/posts?location=Massachusetts&p=2&type=Article
back to top