Library filed under Erosion from Maryland

Garrett wind project fined by MDE

White Construction, Synergics Roth Rock Energy LLC finalized a settlement agreement to resolve alleged sediment control violations that occurred during the construction of the Roth Rock Wind Farm near Red House. The agreement requires White Construction to pay a $35,000 penalty to the Clean Water Fund.
22 Nov 2011

Garrett wind project halted temporarily over mud runoff

Maryland's first industrial wind farm has gotten off to a rough start, with construction temporarily halted after environmental regulators discovered mud washing from the remote Garrett County mountaintop site into a tributary of one of the state's wild and scenic rivers. Constellation Energy has scrambled to put in stronger erosion controls as it erects more than two dozen 400-foot-tall turbines along an eight-mile stretch of Backbone Mountain.
2 Apr 2010

Water runoff issues stall Garrett wind farm construction

Construction on Western Maryland's first wind farm could resume within days, despite some residents' protests, pending a green light from the Garrett Soil Conservation District and the Maryland Department of the Environment. ...MDE spokeswoman Dawn Stoltzfus said construction was halted because of "sediment-laden water" flowing from the site.
30 Mar 2010