Library from Ireland

Environmentalist challenges construction of grid connection to wind farm

Mr Sweetman is seeking an order quashing a decision of An Bord Pleanala in December 2018 that the construction of the connections servicing a windfarm development located at Ballycumber, Tinahealy, Co Wicklow was exempted development. The central issue concerns his the claim that the works undertaken for the purpose of connecting the Ballycumber Wind Farm to the national electricity grid should have been subject to an environmental impact assessment.
27 May 2019

Dispute between wind farm company and farmer over access settled, but another to come

A dispute between a wind farm company and a farmer over an agreement about access to his land for cabling has been struck out at the Commercial Court following mediation talks. However, a second wind farm operator which says it also has a similar access agreement with the farmer is now set to bring proceedings after it expressed disappointment that a deal had been done.
9 Apr 2019

Wind farm regulation cannot just be hot air

The issue only came to light following investigations by local people over what they considered to be excessive noise pollution. So far, so straightforward. Last November, An Bord Pleanála ruled that it constitutes an unauthorised development. Now, the enforcement order has been issued and the developer has six months to comply with the planning permission. As might be expected, the developer has applied to retain the structures.
5 Apr 2019

‘Unauthorised’ wind farm told to cease operations

A wind farm which was not built according to planning permission has been issued with an enforcement notice to cease operations. Barnafaddock Wind Farm in Ballyduff Upper, Co Waterford, was built using turbine 103m-diameter blades. It had permission for 90m-diameter blades. Last November, An Bord Pleanála ruled that the wind farm constituted an unauthorised development because of the anomaly.
5 Apr 2019

Connection delays may scupper 16 wind energy projects

A total of 16 wind energy projects – with full planning permission and grid connection offers – “are at medium or high risk of not being built” ...The problem is arising because connection dates project developers have been offered are all for late 2019, according to IWEA chief executive Dr David Connolly. To qualify for renewable energy feed-in tariff (REFIT) schemes, they need to be built, connected and exporting electricity by March 31st, 2020.
10 Dec 2018

Mayo wind farm project takes on shades of Corrib controversy

A recent series of protests by a small number of people living close to the site at Bellacorick has highlighted wider concerns about the developers’ approach. “North Mayo has learned the meaning of community but the handling of this wind-farm project so far shows the State clearly has not,” says Brendan Lavelle of Keenagh Community Development.
19 Nov 2018

Could wind farms wipe out BIRDS?

Populations are much smaller close to turbines because their habitat has been ruined, study finds; Clearing habitats to make wind turbines is killing off birds in Ireland; Populations were ten per cent lower in areas close to wind turbines; Forest species such as chaffinches, great tits and gold-crests were worst hit
25 Oct 2018

'Wind energy sector must engage with communities over turbines'

The wind energy sector has been told it must engage in real consultation with communities and avoid "disinformation" if wind turbines are to become acceptable to local people. ..."In many cases I could see the proposed locations were in areas of high amenity or areas of conservation, places they would never get permission for turbines.
20 Oct 2018

Endangered Hen Harrier on Donegal wind farm site should have been verified

The Irish Raptor Study Group has been granted permission to bring judicial review proceedings challenging a decision of An Bord Pleanála to grant planning permission for a 19-turbine wind farm located at Meenbog in South Eastern Donegal. ...They claimed that while the developer in its application did not identify the presence of breeding Hen Harrier on the wind farm site IRSG volunteers had identified two pairs of breeding Hen Harrier in the same area.
5 Sep 2018

http://www.windaction.org/posts?location=Ireland
back to top