Library from Illinois

Lawsuit filed to keep turbines from taking root

This land is set to become a wind farm, but dozens are suing the county to stop it from being built. Almost 40 residents have signed onto the lawsuit. They say their rights have been violated, specifically their right to due process. Landowners say the county zoning board didn't provide enough notice for meetings about the project and they feel their voices are being ignored. 
9 Dec 2015

Boone County Illinois wind ordinance

Newwecsordinance-boonecountyil_thumb Following 9 months of testimony and cross examination as well as supportive votes cast by the Boone County zoning board of adjustment, the full county board met and passed this wind energy ordinance with a 9 to 3 margin. The ordinance provides for several protective provisions including establishing setback distances of 2,640 feet or 5.5 times the height of the wind turbine including the blades at the highest point, whichever is greater. A protion of the ordinance is provided below. The full document can be accessed by clicking the links on this page.
15 Nov 2015

Planning, Zoning and Building Committee OKs wind turbine ordinance changes

The Boone County Planning, Zoning and Building Committee on Wednesday voted 4-1 to recommend an amendment to an ordinance governing where wind turbines can be placed in relation to property lines. ...The revised ordinance states that wind energy conversion systems must be at least 2,640 feet, or 5.5 times the height of the turbine tower, away from a property line. The current ordinance states that wind turbines must be 1,000 feet from a residence.
5 Nov 2015

Gov't doesn't owe fees In wind farm row, judge says

An Illinois federal judge on Wednesday nixed a bid for attorneys' fees by property owners and renters in a dispute with the federal government over the environmental implications of a proposed tribe-backed wind farm, saying that eligibility issues among the individual plaintiffs had muddied the waters. 
5 Nov 2015

County committee advances wind farm to full board

 It will now be up to the full Macon County Board to determine whether to allow the construction of more than 100 wind turbines. ...“I don't think we're asking you to vote 'no' and stop this thing and throw it out the window,” he said. “But for those of us who live here, it feel it's getting pushed through here all of a sudden.”
21 Aug 2015

More answers needed on wind turbine plans

Residents asking questions were told loudly, many times by E. ON's lawyer; "There is no risk." Property values will not be affected, noise is not a problem, flickering and other health issues just don't exist. I find that very interesting when there are a number of current lawsuits pending in multiple states and documented studies by experts that say otherwise. ...I think we deserve answers before our county approves their application.
20 Aug 2015

Rights of township in question

A single action item on the Livingston County Board’s agenda Thursday night drew an hour-long debate over the legal and economic ramifications of its passage. The Board ultimately decided to table the item, which concerned Indian Grove Township requesting an ordinance change for its own specific township.
15 Aug 2015

Logan County Board approves wind farm on 8-4 vote

Changes made by developers of a wind farm that the Logan County Board rejected in January were enough to win project approval on a second vote. The board voted 8-4 at a Tuesday night meeting in favor of granting a conditional use permit to the controversial $400 million development.
22 Jul 2015

Major wind farm to get second Logan County vote

Board Chairman David Hepler said Monday commissioners are prepared for large turnouts at an initial board meeting scheduled for Thursday at the Logan County Courthouse and at a second meeting scheduled for Tuesday, July 21, when a board vote is anticipated. Both meetings are scheduled for 7 p.m.
13 Jul 2015

Zoning Board split on wind farm vote

The Logan County Zoning Board of Appeals came up with a two-to-two tie vote on a conditional use permit for the Meridien wind farm project on Wednesday. As a result, the project will go before the Logan County Board on July 16 and 21 with just five conditional recommendations from the ZBA.
10 Jul 2015

http://www.windaction.org/posts?location=Illinois&p=6
back to top