Library from Illinois

Lake Land board to weigh future of wind turbine

Bullock said the southernmost wind turbine of Lake Land's two 160-foot-tall, 100-kilowatt turbines was damaged by a lightning strike last summer and has not functioned properly since then. He said the administration does not believe that making the nearly $100,000 in repairs estimated for the turbine would be cost effective.
8 Apr 2016

Woodford holding wind farm accountable

In an attempt to push the company into action, the committee hired an independent firm, Patrick Engineering, in November 2015 to do a cost study and write a decommissioning plan. The action is allowed under the special use permit with Minonk LLC paying the cost of the study. A copy of the report, which indicated the security deposit should be $15,135,851, was sent to Minonk Wind Farm LLC, which did not respond.
28 Mar 2016

Contract with wind farm developer calls for millions in escrow

The co-developer of a wind farm planned for northern Ford County and southern Kankakee County said that an escrow agreement approved by the Ford County Board last week calls for the developers to provide several million dollars in financial security to Ford County to cover repairs and improvements to public roads used to build the wind farm.
23 Mar 2016

Green energy claims under scrutiny in Illinois

​"As a matter of physics, unless a customer's residence is directly connected to a wind farm or solar panels," electricity suppliers "cannot truthfully claim that they are providing electricity generated from renewable resources," the attorney general's office is quoted as saying in the administrative law judges' proposed order in January.
8 Mar 2016

Let the energy markets work

It seems like we haven't learned much of anything as we continue to interfere in various energy markets. ...First, solar and wind power benefit from a production tax credit, which is simply a subsidy based on the amount of electricity produced. Coupled with various state laws that effectively force grid operators to purchase electricity from solar and wind generation whether or not it is needed, greenhouse gases may actually increase.
28 Feb 2016

Wind project stalled by lawsuit, mitigation pacts; Permit extensions pending in Lee, Whiteside counties

Work slowed in July 2013, when a lawsuit was filed by 60 residents against Lee County and the previous owner, Mainstream. The court challenges cited nonconforming land-use issues, the turbines' effect on property values, and concerns about noise and shadow flicker. The delays have led to the expiration of special-use permits granted by the counties. The permits expired Aug. 26, 2015, in Whiteside County, and they are set to expire in mid-May in Lee County.
20 Feb 2016

‘Time to stand up ...’

When wind energy development first darkened the door of Bureau County several years ago, there really wasn’t that much information available as to the adverse side effects these projects brought with them. That is no longer the case. The horror stories that used to be happening somewhere else are now being experienced on a daily basis by our very own citizens and residents of Bureau County. The elected officials that brought us the first wind development claimed, and rightfully so, “We didn’t know.” The time has now come for this county board to stand up.
8 Jan 2016

Taxpayers are funding the wind-energy hype

The article paints a picture of renewable energy’s future being threatened by land owners who unpatriotically are hampering attempts to build electrical transmission lines from wind-rich Western states to customers. ...It [the transmission] has not been proven necessary by any state’s regulatory commission.
1 Jan 2016

Zoning board denies wind turbines applications

The ZBA explicitly found the standards for granting the permits had not been met and to the contrary, the turbines “would be detrimental to or endanger the public health, safety, moral, comfort, or general welfare.” Further, the turbines “would be injurious to the use and enjoyment of those who own property in the footprint of the project and would have a negative impact on their property values” and “will impede the normal and orderly development of the surrounding property.”
30 Dec 2015

Walnut Ridge permits: Denied!

After nearly a year of public hearings, the Bureau County Zoning Board of Appeals last week made a recommendation to the Bureau County Board to deny conditional use permits for the proposed Walnut Ridge Wind Farm. ...the zoning board of appeals also recommended denial of an extension request of the 2008 conditional uses permits that were previously extended in 2011 and requested again in 2014.
22 Dec 2015

Landowners demand court review of wind farm project

Macon County officials failed to provide statutory notices for a public hearing as well as essential information in-regard to the proposed wind farm project, a petition for review filed by landowners near the project’s location claims. ...Other issues the claim raises includes how residents who sought information on Twin Forks’ application were not given a copy until after the initial Zoning Board of Appeals meeting, which the case states prevented opposition from gathering information and providing its own experts to speak to the county board on the potential negative impact of the project.
9 Dec 2015

http://www.windaction.org/posts?location=Illinois&p=5
back to top