SSE beats Fluor in £300m wind farm legal fight

The case centres on work carried out on 52 of the 140 turbines, with Fluor claiming there was a design change which amounted to a change in specification, meaning it should be paid for the resulting costs. ...SSE expects Greater Gabbard Offshore Winds will continue to pursue its claim against Fluor regarding the structural integrity of the 52 disputed turbines.
20 Nov 2012