Library from Canada

Renewable sector on hold in Alberta

“There’s a lot of uncertainty right now on what programs might be rolled back, what incentives might be rolled back, so that creates not a great environment for investors,” said Binnu Jeyakumar, director with the Pembina Institute. “There’s a lot of wait and see. What we saw in Ontario was pretty disastrous for investments” in renewable energy, she added.
23 May 2019

Hydro-Québec poised to profit from U.S. thirst for green energy

“The contract with New York is far from being signed,” Pineau said. “The mayor of New York City has said he wants to start negotiating, so that’s a very good sign. If he goes public it means he’s committed. … But it’s never easy. In principle everyone loves renewable energy, but when it comes to the invoice and the price tag, sometimes people have second thoughts.” In the case of New York City, that price tag includes $2.9 billion for U.S. developers to run the line through the state of New York, plus hundreds of millions more for Hydro-Québec to bring the line from the border to the Hertel converter station on Montreal’s South Shore.
9 May 2019

Residents living near wind farm fed up with constant banging noise from damaged blade

Residents living near the Sumac Ridge Wind Farm say a damaged blade isn’t the only thing that’s been left blowing in the wind. The are fed up with the dangling piece of metal hitting the turbine and making a loud banging noise for the past two weeks. They are calling on the owners to repair it immediately saying it’s causing headaches and keeping then up at night.
30 Apr 2019

Sumac Ridge wind turbine manufacturer files for insolvency

Senvion, the German company behind the Sumac Ridge turbine project in Kawartha Lakes, filed for insolvency just days before a Pontypool-area turbine failed on April 20. ...Financial sources had told Reuters that the Hamburg-based company needed at least 100 million euros ($112 million) in the short term to keep operating.
29 Apr 2019

Answers still sought on CS Wind

The Ontario Ministry of Labour has confirmed that the plant is in a “state of shutdown”, but there is still no word on whether the shutdown is temporary or permanent. The City of Windsor, which offered the company millions of dollars in incentives to set up shop in the city, is among those trying to get answers.  However, city officials have not made much headway.
22 Mar 2019

Wind turbine catches fire at Nova Scotia wind farm

Firefighters were unable to get close enough to put the fire out directly because of the turbine's height and movement of the blades -- and it couldn't be turned off with the gearbox on fire. "It was too dangerous to get close to it," Amiro said. "Because of the length of the blades and the blades were turning, you didn't know where they were going to go when they fell."
16 Mar 2019

Wait continues to frustrate Water Wells First group

Water Wells First members were once optimistic after a promise made by Ontario Progressive Conservative Party Leader Doug Ford during last year’s provincial election campaign that a health-hazard investigation would be initiated if he was elected premier. However, since the citizens’ group received that promise in writing from Ford last May, its members continue to wait for this investigation to start.
15 Mar 2019

CS Wind stops producing wind turbines in Windsor

Hundreds of people are out of work after CS Wind, which moved to Windsor with great fanfare and $10 million in incentives, shut down its local factory. ...MacPherson said the explanation he heard for the shutdown was a lack of work after the province cancelled hundreds of renewable energy contracts.
14 Mar 2019

Wind farm equipment removed

Cancelling 758 renewable energy contracts—including Otter Creek– was one of the first moves of the newly elected Progressive Conservative party after they were elected in the spring of 2018. The project was expected to be built and commissioned by the end of 2019.  
14 Feb 2019

Wind energy may be green, but the water in Chatham-Kent is brown

Residents realized their worst fears as the project began the construction phase last summer. Nineteen wells began to experience sediment problems, Jakubec says — nearly a third of the 64 wells that the group members had tested at their own expense. Bill Clarke, a hydrogeologist for Water Wells First who gathered and analyzed the samples, says follow-up testing showed the affected wells experienced changes in water turbidity, amount of particles, colour, and rate of flow.
12 Feb 2019

http://www.windaction.org/posts?location=Canada
back to top