The attached communications between the Bureau of Land Management (BLM) and Iberdrola/Tule Wind detail the BLM's notice to suspend construction of the 186 MW wind project due to repeated violations of the right-of-way permit issued by the BLM. The Tule facility initiated construction on December 6, 2016. The notice to stop construction was issued on January 20, 2017. Construction has now resumed. Both the notice to suspend construction and to resume construction, which includes Iberdrola's response to the BLM, can be accessed by selecting the document links on this page, A portion of BLM's notice is provided below.