OCC addresses controversial wind turbine construction

News 9|Karl Torp|September 18, 2018
OklahomaLegalSafety

NextEra is building more than 160 turbines, and many neighbors say they are do it illegally. “The law is very clear,” said attorney Kim Spady, who represents some neighbors from Hinton.


HINTON, Oklahoma - The Oklahoma Corporation Commission heard concerns Tuesday about a wind farm near the town of Hinton.

NextEra is building more than 160 turbines, and many neighbors say they are do it illegally.

“The law is very clear,” said attorney Kim Spady, who represents some neighbors from Hinton.

Spady points to the new law which took effect in May.

It states a wind developer must obtain what's called a "no hazard" determination for each turbine from the Federal Aviation Administration or work out a mitigation plan with the Department of Defense and submit notification to the Oklahoma Corporation Commission.

“They would be okay if they were building the turbines they filed for in 2016, but those aren't the turbines …

... more [truncated due to possible copyright]

HINTON, Oklahoma - The Oklahoma Corporation Commission heard concerns Tuesday about a wind farm near the town of Hinton.

NextEra is building more than 160 turbines, and many neighbors say they are do it illegally.

“The law is very clear,” said attorney Kim Spady, who represents some neighbors from Hinton.

Spady points to the new law which took effect in May.

It states a wind developer must obtain what's called a "no hazard" determination for each turbine from the Federal Aviation Administration or work out a mitigation plan with the Department of Defense and submit notification to the Oklahoma Corporation Commission.

“They would be okay if they were building the turbines they filed for in 2016, but those aren't the turbines they are building,” said Spady, who says NextEra has already completed 36 of the planned turbines.

After hearing concerns, including how the turbines could affect military training routes, The Oklahoma Corporation Commission addressed the issue at a meeting Tuesday.

Read Also: Hinton Wind Fighter Reaches Air Force

Commissioner Todd Hiett called it the start of the exploratory phase.

“As part of the wind development act, I believe we do have some oversight ability to these projects,” said Commissioner Hiett.

OCC's Public Utility Division feels the NextEra's paperwork filed in 2016 is still good for the turbines being built now, even if their locations have slightly changed.

NextEra’s attorney says the determination for “no hazard” was renewed through April 2019.

The three Commissioners can trump what OCC's Public Utility Division has concluded.

Meanwhile, NextEra moves forward with construction.

“I don’t know why the Corporation Commission is reluctant to enforce this law,” said Spady.


Source:http://www.news9.com/story/39…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION