logo
Article

High Court quashes planning board refusal of wind farm on Kildare-Meath border

TheJournal.ie |September 29, 2017
IrelandImpact on PeopleLegal

The court said it was setting aside An Bord Pleanala’s decision on grounds including that irrelevant considerations were taken into account by the planning authority when it turned an application by Element Power Ireland Ltd to develop the project.


The High Court has “quashed in its entirety” a refusal by An Bord Pleanala to grant planning permission for a 47-turbine wind farm on the Kildare-Meath border.

In his judgment today, Mr Justice Robert Haughton ruled that the application for the Maighne wind farm should be remitted back to An Bord Pleanala for reconsideration.

The court said it was setting aside An Bord Pleanala’s decision on grounds including that irrelevant considerations were taken into account by the planning authority when it turned an application by Element Power Ireland Ltd to develop the project.

In 2015 the developer had sought planning permission from the board to construct the turbines – 45 in north-west Co Kildare and two in Co Meath, as well as an …

... more [truncated due to possible copyright]

The High Court has “quashed in its entirety” a refusal by An Bord Pleanala to grant planning permission for a 47-turbine wind farm on the Kildare-Meath border.

In his judgment today, Mr Justice Robert Haughton ruled that the application for the Maighne wind farm should be remitted back to An Bord Pleanala for reconsideration.

The court said it was setting aside An Bord Pleanala’s decision on grounds including that irrelevant considerations were taken into account by the planning authority when it turned an application by Element Power Ireland Ltd to develop the project.

In 2015 the developer had sought planning permission from the board to construct the turbines – 45 in north-west Co Kildare and two in Co Meath, as well as an electricity substation, underground cables, and 31km of access tracks.

In October 2016 the board refused to grant permission for the development. The proposed turbines were to be developed in five clusters and would be 169 metres high.

In its decision, the board said it was turning down the proposal on grounds including that in the absence of any national wind energy strategy with a spatial dimension, the plan would be premature.

It would, the board said, represent an undesirable precedent that could undermine any future strategy for the area.

Other reasons cited by the board included that the project, which consists of widely dispersed cluster-based wind farms, would have an adverse effect on the local residences and heritage, and would have a long-term significant adverse effects on the structural integrity of the local road network.

Element Power challenged the board’s refusal on grounds including that planning authority had acted outside of its powers, and that its decision in relation to the lack of a national wind energy strategy was too vague and unclear to be adequate.

In a detailed and lengthy judgment, Mr Justice Haughton held that the board had acted outside of its powers and had taken irrelevant considerations into account when it decided to refuse permission on the basis of a lack of a national wind energy strategy.

The Judge said that a wind energy policy was contained in two relevant county developments plans. However in its decision to refuse it appeared to the court that the board failed to address by reference to those plans if it should grant permission.

The Judge also found that the board had fettered its discretion when it determined that the proposed development was premature pending the implementation of a national wind energy strategy.

In all the circumstances the Judge said he was satisfied to quash the decision in its entirety and sent the matter back for reconsideration, the judge added.

 


Source:http://www.thejournal.ie/high…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION