Another turbine failure has been reported at Michigan's Deerfield wind facility in Huron County. The Deerfield project includes a mix of Vestas V110 2MW and 2.2MW machines for a total installed capacity of 150 MW. Two blades on separate turbines broke in half in late 2016 when the project was in the process of being commissioned. There was “an anomaly in the manufacturing process that resulted in a cavity in the blade shell support structure where the blades broke,” Vestas told reNEWS. Fifty blades in the 72-turbine facility shared the same flaw. No information is available on the cause of this recent failure.