logo
Article

Residents and activist challenge permission for wind farm project

The Irish Times|Aodhan O'Faolain and Ray Managh|August 2, 2014
IrelandGeneral

A High Court challenge has been brought against An Bord Pleanála’s decision to grant planning permission for a large wind farm development in the midlands.


A High Court challenge has been brought against An Bord Pleanála’s decision to grant planning permission for a large wind farm development in the midlands.

Last June the planning board granted Green Wind Energy (Wexford) Ltd permission to build 29 electricity generating wind turbines with a maximum height of up to 166m (545ft), plus ancillary buildings, all on a site just north of Rhode, Co Offaly.

In High Court proceedings challenging that decision local residents Stephen Carroll of Croghan, Rhode, and Joanne Addie Ballyburley Rhode, and environmentalist campaigner Peter Sweetman of Cashel Co Galway say the decision is flawed and should be quashed.

The planning board found that while accepting that the proposal would be visually …

... more [truncated due to possible copyright]

A High Court challenge has been brought against An Bord Pleanála’s decision to grant planning permission for a large wind farm development in the midlands.

Last June the planning board granted Green Wind Energy (Wexford) Ltd permission to build 29 electricity generating wind turbines with a maximum height of up to 166m (545ft), plus ancillary buildings, all on a site just north of Rhode, Co Offaly.

In High Court proceedings challenging that decision local residents Stephen Carroll of Croghan, Rhode, and Joanne Addie Ballyburley Rhode, and environmentalist campaigner Peter Sweetman of Cashel Co Galway say the decision is flawed and should be quashed.

The planning board found that while accepting that the proposal would be visually prominent in some views, it concluded that the visual impact would be acceptable.Planning board approves €80m wind farm in Tipperary

Inadequate assessment They claim an inadequate environment impact assessment (EIA) was carried out by the planning authority before consent was given.

They allege the EIA conducted by the board failed to identify, describe and assess the direct and indirect effects the development will have on people, flora and fauna, soil, water, air climate and the landscape.

It is also claimed that in compiling the EIA the planning authority failed to properly take into account submissions made by members of the public during the consultation process.

In their proceedings against the board the residents, who are members of the Rhode Parish Wind Turbine Action Group, and Mr Sweetman are seeking an order quashing the board’s decision to grant permission for the proposed wind farm.

Breaches They are also seeking a number of declarations, including that the decision breaches EU directives on the effects certain projects have on the environment.

They also seek a declaration from the court that a proper EIA, as required under EU directives, was not carried out by the board before permission was granted.

They have secured leave from Ms Justice Marie Baker in the High Court to challenge the decision. Permission was granted on an ex parte basis, where only one side was represented in court.

Offaly County Council and Green Wind Energy Ltd are notice parties to the proceedings.

The case will return before the High Court in November.


Source:http://www.irishtimes.com/new…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION