GE 1.6 MW turbines dominate Michigan's landscape

DTE Energy's 112 MW Echo Wind project is under construction in the townships of Elkton, Chandler, and Oliver in Michigan's Huron County. Construction of the wind facility's 70 GE 1.6 MW wind turbines was completed in mid-October. GE's commissioning of the project was scheduled to be completed by the end of November. The company suspended commissioning activities after experiencing a catastrophic blade failure on Nov. 7, 2013.

FEB 27 2014
http://www.windaction.org/posts/39930-ge-1-6-mw-turbines-dominate-michigan-s-landscape