Grid constraints may hamper NEK wind proposal

Vermont Public Radio|John Dillon |August 20, 2013
VermontTransmission

David Hallquist, the CEO of the Vermont Electric Cooperative, said the Eden Wind turbines would exacerbate the transmission bottleneck. Hallquist said expensive upgrades would be needed to accommodate the 18 megawatts from Eden. "...I can’t imagine any developer spending what could amount to be a hundred million dollars in investment just to put their project on line."


A Connecticut company wants to develop a new wind project on a Northeast Kingdom ridgeline just south of an existing wind development.

But there’s growing concern that the transmission grid in the region is not strong enough to handle more large-scale wind generation.

BNE Energy of Colebrook, Ct. wants to erect six turbines, each capable of producing three megawatts, along the spine of the Lowell Mountains. The site in Eden is adjacent to Green Mountain Power’s 21-turbine Kingdom Community wind project.

BNE Paul Corey said the company has measured the wind resource in Eden and has a long-term lease on 350 acres. BNE recently submitted the Eden proposal to generate power for Connecticut utilities to meet that state’s renewable energy …

... more [truncated due to possible copyright]

A Connecticut company wants to develop a new wind project on a Northeast Kingdom ridgeline just south of an existing wind development.

But there’s growing concern that the transmission grid in the region is not strong enough to handle more large-scale wind generation.

BNE Energy of Colebrook, Ct. wants to erect six turbines, each capable of producing three megawatts, along the spine of the Lowell Mountains. The site in Eden is adjacent to Green Mountain Power’s 21-turbine Kingdom Community wind project.

BNE Paul Corey said the company has measured the wind resource in Eden and has a long-term lease on 350 acres. BNE recently submitted the Eden proposal to generate power for Connecticut utilities to meet that state’s renewable energy requirements.

“We feel it’s a very good location for a wind project, and it would help mitigate environmental impacts being on the same location as Kingdom Community wind,” Corey said.

While the winds may be strong on the Lowell ridgeline, the nearby transmission network is weak, as Green Mountain power has learned.

The operator of the New England transmission grid has periodically ordered GMP to cut back the power produced by Lowell out of concern that the grid could get overloaded and fail. The same situation has also affected the Sheffield project in the Northeast Kingdom.

David Hallquist, the CEO of the Vermont Electric Cooperative, said the Eden Wind turbines would exacerbate the transmission bottleneck. Hallquist said expensive upgrades would be needed to accommodate the 18 megawatts from Eden.

“Because it’s already constrained by Kingdom Community Wind and Sheffield,” he said. “And that [Eden] project would end up at the same point in Irasburg that those other two wind projects are on. And I can’t imagine any developer spending what could amount to be a hundred million dollars in investment just to put their project on line."

Hallquist said Vermont Electric would oppose the Eden proposal, just like it’s raised concerns about another proposal in the Northeast Kingdom called Seneca Mountain Wind.

“We’re opposed to any additional wind projects, or any additional generation at all in that constrained transmission system,” he said.

Other opposition is likely from residents concerned about the impact on the ridgeline ecosystem and wildlife habitat. Steve Wright from Craftsbury is a former Fish and Wildlife commissioner who worked against the GMP project in Lowell.

“There are all sorts of issues. One issue being connection issues as is normally is the case throughout the Northeast Kingdom and north central Vermont,” he said. “There’s also a major wildlife management area on the southeastern flank of the ridgeline, the Wild Branch Wildlife Management Area with significant bear, moose, and brook trout populations.”   

Paul Corey of BNE Energy said the project can be built with minimal environmental impact. But transmission constraints are a concern, he said.

“We believe there are a couple of different alternatives. And it [the power generated at Eden] wouldn’t be tying into what Green Mountain constructed, it would essentially be going a different route,” he said.

Corey said depending on the outcome of the Connecticut bid process his company could be filing for permits sometime next year.


Source:http://digital.vpr.net/post/g…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION