logo
Article

State to fall short of wind power goal, studies say

Maine Center for Public Interest Reporting|Naomi Schalit and John Christie|March 30, 2012
MaineGeneral

Maine will not be able to accomplish the state-mandated goal of building 2000 megawatts of wind power on land by 2015. That's one conclusion of two studies issued this week by the governor's energy office and an independent group of researchers. The studies also urged reconsideration of the landmark 2008 law that allowed wind turbines to be built in ecologically and scenically important areas of the state.


The two studies also urge reconsideration of the Wind Energy Act of 2008.

Maine will not be able to accomplish the state-mandated goal of building 2000 megawatts of wind power on land by 2015.
 
That's one conclusion of two studies issued this week by the governor's energy office and an independent group of researchers.

The studies also urged reconsideration of the landmark 2008 law that allowed wind turbines to be built in ecologically and scenically important areas of the state.

"No one imagines that we'll be meeting the goal at 2015," said Stephen Ward, co-author of "Maine Wind Assessment 2012." "In order to meet the 2015 goal, at least 552 new turbines will have to be permitted and become operational by 2012, and -- depending on …

... more [truncated due to possible copyright]

The two studies also urge reconsideration of the Wind Energy Act of 2008.

Maine will not be able to accomplish the state-mandated goal of building 2000 megawatts of wind power on land by 2015.
 
That's one conclusion of two studies issued this week by the governor's energy office and an independent group of researchers.

The studies also urged reconsideration of the landmark 2008 law that allowed wind turbines to be built in ecologically and scenically important areas of the state.

"No one imagines that we'll be meeting the goal at 2015," said Stephen Ward, co-author of "Maine Wind Assessment 2012." "In order to meet the 2015 goal, at least 552 new turbines will have to be permitted and become operational by 2012, and -- depending on the size of the turbines -- potentially as many as 1,103 turbines will be needed."

The state is "making progress, though, in meeting the off-shore wind goals for 2020 and 2030," says Ward's report, produced by Coastal Enterprises, Inc. for the Office of Energy Independence and Security. No off-shore wind farms have been built.

Maine has eight large-scale, land-based wind projects producing a total of 345.5 megawatts and five more projects in the pipeline that will generate 300.8 additional megawatts.

Ward's report, in turn, formed the basis of a report given Wednesday to a legislative committee by Ken Fletcher, head of the governor's energy office.

That report, "Maine Wind Energy Development Assessment," also predicts the state's land-based wind-power goals will not be met.

"We're not saying anybody has failed," Fletcher said. "It's just that the economic realities of the economy and the cost structure of wind seems to make it more of a challenge to get to the installed capacity."

Both reports recommend changing state law to reflect more modest goals for 2015.

That worried Jeremy Payne, head of the Maine Renewable Energy Association, which represents the state's wind developers.

"I don't understand the purpose of stepping back from the goal," Payne said. "Why would we want to do that and send a bad signal to the investors -- it's a confusing signal to send to them at the wrong time."

Payne said opponents of wind projects who mount legal appeals were to blame for slow progress toward Maine's wind development goals. "You're talking years upon years to get a decision," he said.

The reports were done at the behest of legislators on the Utilities and Energy Committee who wanted a review of the Wind Energy Act.

The act was the product of a task force of wind energy supporters empaneled by then-Gov. John Baldacci, a strong booster of wind power. It gave developers a fast track to putting up wind turbines in some of the state's treasured landscapes, including sensitive ecological areas above 2,700 feet, and established aggressive goals that would have placed up to 2000 turbines on Maine's landscape by 2030.

The map of that "Expedited Wind Zone" was put together by the task force in closed-door meetings for which no written records were kept. The Coastal report said that redoing the map with a more diverse group would be a good idea.

"The Governor, the Legislature or DEP could convene a panel of disinterested parties to identify where in Maine expedited permitting could go forward in a way that causes no harm to local residents or environments," the authors wrote.

The report also says the conflict that's arisen in recent years over siting of wind tower projects might be addressed by a different -- more public -- process.

"It may also be desirable to convene a group that is not composed entirely of interested stakeholders as also was the case in 2007," the report says.

Fletcher's report recommended lawmakers find better ways to evaluate the visual impacts of wind towers ... and adopt policies requiring consideration of the cumulative impacts of multiple wind developments.

And the Coastal report notes that while two state agencies -- the Land Use Regulation Commission and the Maine Historic Preservation Commission -- recognize sporting camps as "an iconic and historic cultural resource" worthy of protection from development, the state's wind power laws do not, and perhaps should.

"We need to find an appropriate balance and process, not that we don't want to do projects," Fletcher said.


Source:http://www.pressherald.com/ne…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION