UD wind turbine generates federal suit; Lewes resident seeks damages, jury trial

Cape Gazette|Henry J. Evans Jr.|January 28, 2012
DelawareImpact on People

Lechliter alleges the university obtained permits for the turbine "based on backroom negotiations with DNREC and the City (Lewes) and its public misrepresentations that the wind turbine would cause no intrusive noise and not result in diminution of property values."


A Lewes resident has filed a lawsuit in federal district court alleging the University of Delaware violated law in obtaining permits for its wind turbine.

Lewes - A lawsuit has been filed seeking injunctive relief and damages in connection with construction of the University of Delaware's wind turbine near the College of Earth, Ocean and Environment campus in Lewes.

The lawsuit alleges the wind turbine was built on open space lands in violation of law. The action states defendants obtained permits for the wind turbine based on misrepresentations.

Lewes resident Jerry Lechliter filed the action against the University of Delaware, Delaware Department of Natural Resources and Environmental Control, City of Lewes, U.S. Department of …

... more [truncated due to possible copyright]

A Lewes resident has filed a lawsuit in federal district court alleging the University of Delaware violated law in obtaining permits for its wind turbine.

Lewes - A lawsuit has been filed seeking injunctive relief and damages in connection with construction of the University of Delaware's wind turbine near the College of Earth, Ocean and Environment campus in Lewes.

The lawsuit alleges the wind turbine was built on open space lands in violation of law. The action states defendants obtained permits for the wind turbine based on misrepresentations.

Lewes resident Jerry Lechliter filed the action against the University of Delaware, Delaware Department of Natural Resources and Environmental Control, City of Lewes, U.S. Department of Energy, Gamesa Technology Corp., Blue Hen Wind Inc., and individuals associated with those agencies.

Lechliter alleges the university obtained permits for the turbine "based on backroom negotiations with DNREC and the City (Lewes) and its public misrepresentations that the wind turbine would cause no intrusive noise and not result in diminution of property values." The action seeks damages in excess of $250,000 together with costs and further relief as the court deems just.

Lechliter, representing himself in the action, filed the 40-page lawsuit Jan. 9 in U.S. District Court for the District of Delaware in Wilmington.


Source:http://capegazette.villagesou…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION