Scenic-view decision casts cloud over wind prospects

Recharge News|Benjamin Romano|January 17, 2012
WashingtonImpact on LandscapeImpact on Views

In its reconsideration petition, which the EFSEC declined last month, WRE says the scaled-down project - with 15 turbines eliminated - would probably not be economically viable, partly because there is no room for larger turbines that could return the wind farm to its proposed capacity.


A decision by Washington state siting authorities to protect scenic views calls into question the state's process for reviewing wind-energy projects.

The state Energy Facility Site Evaluation Council (EFSEC) has declined to reconsider its October decision, which approved the 75MW Whistling Ridge wind project near the Columbia River Gorge National Scenic Area, but ordered it to be reduced by 30%. The decision moves what would be the first wind farm on commercial timberland in the Evergreen State "further away from viability".

Both the developer, Whistling Ridge Energy (WRE), along with local governments supporting the project, and opponents, including Friends of the Columbia Gorge and the Seattle Audubon Society, had asked the EFSEC to …

... more [truncated due to possible copyright]

A decision by Washington state siting authorities to protect scenic views calls into question the state's process for reviewing wind-energy projects.

The state Energy Facility Site Evaluation Council (EFSEC) has declined to reconsider its October decision, which approved the 75MW Whistling Ridge wind project near the Columbia River Gorge National Scenic Area, but ordered it to be reduced by 30%. The decision moves what would be the first wind farm on commercial timberland in the Evergreen State "further away from viability".

Both the developer, Whistling Ridge Energy (WRE), along with local governments supporting the project, and opponents, including Friends of the Columbia Gorge and the Seattle Audubon Society, had asked the EFSEC to reconsider its decision.

The EFSEC order has been sent to Governor Christine Gregoire, a renewables proponent in her final year in office, who must accept, reject or return it to the EFSEC, with modification instructions, by 5 March.

Opponents argue that even the scaled-down project should be denied a permit because it would spoil views from within the scenic area. Supporters want it to go ahead as proposed - with 38-50 turbines capable of generating 75MW - to bolster the economy of rural Skamania County and advance the state's renewables goals.

In its reconsideration petition, which the EFSEC declined last month, WRE says the scaled-down project - with 15 turbines eliminated - would probably not be economically viable, partly because there is no room for larger turbines that could return the wind farm to its proposed capacity.

Jason Spadaro, president of WRE and SDS Lumber, which owns the land, says the EFSEC decision has delayed construction and made it smaller. That moves the project "further away from viability", but he adds: "That doesn't mean that it would never be able to go forward, either."

The EFSEC says the arguments for reconsideration from both sides are repetitive or irrelevant to its decision. But the developer has raised concerns about the council's process and interpretation of state and federal law.

If this small project - with only moderate or low visual impacts, according to the EFSEC's environmental study - cannot be permitted, the siting process is hopelessly broken "and it is highly questionable whether the council will ever be able to site another wind energy project", the developer argues.


Source:http://www.rechargenews.com/h…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION