Cross-border wind power line faces regulatory delay

Calgary Herald |Dina O'Meara|December 22, 2011
USACanadaTransmission

Power line builder and operator AltaLink was included in Wednesday's decision on the 230-kilovolt transmission line by the Alberta Utilities Commission, having also applied for an extension on its substation project associated with the project. The merchant power line has been in the making for more than five years


A merchant power line linking wind generation in Montana to Alberta's electricity grid will be delayed, but not as long as proponents had applied for.

Provincial regulators denied Enbridge Inc. a request to extend permitting deadlines on the Montana-Alberta Tie Line (MATL) by a year, instead granting the pipe-line and energy giant a regulatory break until May.

Power line builder and operator AltaLink was included in Wednesday's decision on the 230-kilovolt transmission line by the Alberta Utilities Commission, having also applied for an extension on its substation project associated with the project.

The merchant power line has been in the making for more than five years, with original proponents struggling to find contracts in Alberta, …

... more [truncated due to possible copyright]

A merchant power line linking wind generation in Montana to Alberta's electricity grid will be delayed, but not as long as proponents had applied for.

Provincial regulators denied Enbridge Inc. a request to extend permitting deadlines on the Montana-Alberta Tie Line (MATL) by a year, instead granting the pipe-line and energy giant a regulatory break until May.

Power line builder and operator AltaLink was included in Wednesday's decision on the 230-kilovolt transmission line by the Alberta Utilities Commission, having also applied for an extension on its substation project associated with the project.

The merchant power line has been in the making for more than five years, with original proponents struggling to find contracts in Alberta, permits in Montana and financing in Canada and the United States.

The line was expected to flow 340 megawatts of wind-generated power by mid-2012 from Great Falls, Mont., to a substation just north of Lethbridge, anchored by take-or-pay contracts with U.S. developers.

However, in September Enbridge and AltaLink filed separate applications to extend their construction deadlines until Dec. 31, 2012, citing weather and disputes with U.S. land-owners and contractors.

Enbridge was noncommital about the regulator's shortened timeline when contacted Wednesday. "The extension of our construction permit to May 31, 2012, was an interim decision made by the AUC that will allow the commission more time to consider applications that MATL currently has before the commission," an Enbridge spokes-woman, Jennifer Varey, wrote in an e-mail.

This year, the Calgary-based company said it would be investing $300 million for the 2012 launch, followed by a low-cost expansion for 2014.

Enbridge bought the project for $70 million from cash-strapped developer Tonbridge Power Inc. in August, acquiring at the same time legal battles in both countries.

One such battle is in front of a Montana district judge today, a case challenging the MATL's right to force U.S. landowners to cede property under "eminent domain" as unconstitutional.

As a result of the delays, AltaLink was unable to complete construction on the Picture Butte substation needed to connect the transmission line with the provincial grid and also asked for an extension, said spokes-man Scott Schreiner.

The regulator's decision giving until May 31 as an interim deadline while it reviews both applications will be respected, he said. "That's what we'll work with and we'll continue with our construction efforts to be able to get that substation in place by that time," Schreiner said.

The 340-megawatt capacity line was fully contracted by wind power generators, and supported on the U.S. side by a low-cost, 30-year loan from the Western Area Power Ad-ministration of the U.S. Department of Energy.

The $161-million federal stimulus loan could be compromised if the project is delayed beyond April 30, according to MATL proponents.

Back in Alberta, the Alberta Electric System Operator was aware of the commission decision and was planning around it, said spokesman Alan Clay.


Source:http://www.calgaryherald.com/…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION