Picture

Steelwinds turbines undergo repair -- again

Turbines at the Steelwinds facility in Lackawanna, New York are undergoing substantial repair -- again. The Steelwinds Project went online in the summer 2007 with eight Clipper 2.5 megawatt turbines. The project was the first to use the Clipper units, touted as the new standard for reliable performance. By late summer 2007, the facility was shut down due to damage in the turbine gear boxes (http://www.windaction.org/news/13133 ) The repairs occurred in early 2008. This photo taken May 12, 2009 shows the facility down again. First Wind, formerly UPC Wind, has provided no information on the root cause of the turbine failure.

MAY 12 2009
http://www.windaction.org/posts/20285-steelwinds-turbines-undergo-repair-again
back to top