Editorial

Electric grid interconnection request activity

An analysis of grid interconnection requests within U.S. portions of North America reveals that proposed wind energy development as of October 2007 totals up to 164,900 MW. This information, based on data compiled within the last two months, is regionally distributed as follows (rounded to the nearest 100 MW):

Note: Some numbers may be inflated due to occasional multiple interconnection study applications for the same wind energy project. Entry in the queue does not guarantee a project will be built; however, it is an indicator of development activity. (Information compiled by Dan Boone)
OCT 29 2007
http://www.windaction.org/posts/11663-electric-grid-interconnection-request-activity