HONOLULU – With 20 1.5-megawatt wind generators in place, Kaheawa Wind Power is seeking a lease to expand on 325 acres on the slopes above McGregor Point.
The lease request has raised concerns over environmental and visual impacts that have generated criticism from some residents of Maui, according to a report being submitted today to the state Board of Land and Natural Resources.
Kaheawa Wind Power is seeking a negotiated lease for state land adjoining the 200-acre wind farm that went into operation in June. The submittal to the land board meeting this morning in Honolulu includes a recommendation to allow the state Land Division to negotiate a direct lease to Kaheawa Wind Power II LLC with rental of $12,000 a year.
The expansion proposal would add up to 18 wind turbines and supporting equipment capable of producing up to 27 megawatts of electrical power.
Also filed under [
General|
Zoning/Planning]
Kahuku top pick again for wind farm
September 15, 2006 by Mike Gordon and Greg Wiles, Staff Writers in The Honolulu Advertiser
September 15, 2006 by Mike Gordon and Greg Wiles, Staff Writers in The Honolulu Advertiser
An Oregon company wants to build Hawai'i's most powerful wind farm along the Kahuku coast, not far from the green hills where Hawaiian Electric Co. is re-evaluating the area for a wind farm after failing nearby with an earlier project.
West Wind Works LLC wants to build 20 turbines capable of producing 50 megawatts of power on 1,100 acres at the northernmost point of O'ahu, including in an area near the abandoned Kahuku Airfield, said company president Keith Avery.
At the same time, Hawaiian Electric is talking to the military about testing wind patterns near Kahuku and possibly using U.S. Army land for a project.
Also filed under [
General|
Zoning/Planning]
Kahuku wind farm fire spreads concerns over future projects
August 4, 2012 by Tim Sakahara in Hawaii News Now
August 4, 2012 by Tim Sakahara in Hawaii News Now
Aerial shots over the Kahuku wind farm show the warehouse that was filled with 12,000 battery packs severely damaged and releasing toxic smoke and lead into the air. ...First Wind is supposed to submit a cleanup plan to the state by the end of the day which will include samples of the air, soil and water.