The Albemarle County Planning Commission has thrown out the idea of allowing commercial wind turbines in the county-but it's mulling the idea of smaller wind turbines for individual homeowners. ...the devices are behemoths that are up to 550' tall, dwarfing everything around them.
"As I understand it, where they might be adequate, there would be unacceptable environmental consequences to the surrounding area," says Commissioner Jon Cannon. Fellow Commissioner Marcia Joseph echoed Cannon's feelings on commercial wind turbine creation.
"My main concern is lining the ridgeline with commercial-sized wind turbines," says UVA Environmental Sciences Professor Rick Webb. "I'm concerned about industrial scale development intruding on what remains of wilderness areas we have left."
Also filed under [
Impact on Landscape|
North Carolina]
Blowing in the wind: Alternative energy may be on horizon for Shenandoah Valley
April 9, 2008 by Susan Beaver Thompson and Arthur James Maas in Shenandoah Valley-Herald
April 9, 2008 by Susan Beaver Thompson and Arthur James Maas in Shenandoah Valley-Herald
Freedom Works is planning the project to span the ridge line running along the border between Va. and West Va. The line runs from approximately five miles north of Woodstock to about five miles South of Mount Jackson, along the Western horizon. This would cover eighteen miles of ridgeline, in two states (Virginia and West Virginia), and three counties (Hardy in West Virginia, and Shenandoah and Rockingham in
Virginia.)
The timeline for the project runs from as short as a two-year, permit-gathering phase (followed by one to two years of construction) to a completion date as far off as the year 2040. When asked about a reported 2010 completion date for the project, Jim Smalls, district ranger for the Lee Ranger District within which the project is being planned, simply said, "I find that optimistic."
Wind project moving ahead; permit concerns still an issue
April 3, 2008 by James Jacenich in The Recorder
April 3, 2008 by James Jacenich in The Recorder
The Highland New Wind Development wind utility project is moving ahead, H.T. 'Mac' McBride told supervisors Tuesday. "We have approval (from VDOT) for both entrances (state line and cattle crossing on Laurel Fork). The power purchase agreement is being worked on by our people in Minnesota." ...Highland resident Rick Webb told the board, "It has been suggested on multiple occasions that it would be in the county's best interest to require that HNWD develop a habitat conservation plan and obtain an incidental take permit in compliance with the federal Endangered Species Act. The conditional use permit issued by the previous board of supervisors stipulated that HNWD would be required to obtain all required state and federal approvals before the project is allowed to go forward. Both the U.S. Fish and Wildlife Service and the Virginia Department of Game and Inland Fisheries have recommended that HNWD obtain an incidental take permit in order to avoid penalties and possible project shut down. The State Corporation Commission acknowledged that HNWD was assuming a business risk by not obtaining an ITP.
Also filed under [
Zoning/Planning]
Proposals for wind farms in the Valley are whipping up opposing viewpoints about the structures' effects on wildlife, local vistas and energy production.
Opponents say the turbines, each hundreds of feet tall, would mar the local landscape and endanger bats and birds, some of which are federally protected.
But proponents say the farms can be built with minimum impact on the environment to offer clean, alternative energy and a break from the nation's dependency on foreign oil. ...After studying maps and coordinates provided by the Federal Aviation Administration, consultant D. Daniel Boone, a conservation biologist and policy analyst, said the FreedomWorks' project could negatively affect untouched areas of the George Washington National Forest.
"Other than a power line and one small road which crosses between Hardy and Shenandoah counties, the project area is completely undisturbed forest with no sign of logging roads or clear-cuts," Boone stated.
Also filed under [
General|
West Virginia]
Highland citizens have once again reminded county supervisors of their intent to sue the board if proper conditions are not met by Highland New Wind Development LLC.
In a Feb. 27 letter addressed to the board, county attorney Melissa Dowd, county administrator Roberta Lambert, and zoning administrator Jim Whitelaw, the law firm of Woods Rogers outlined the citizens' expectations based on the conditional use permit granted to the developer July 14, 2005.
Attorney James Jennings, writing on behalf of his clients, first contacted the county in July 2005 informing officials that if they granted a building permit to HNWD they could be violating the Endangered Species Act.
Also filed under [
General]
Turbines fan controversy; Proposed wind farm site is home to endangered wildlife
March 2, 2008 by Lauren Fulbright in The News Leader
March 2, 2008 by Lauren Fulbright in The News Leader
In addition to killing birds, wind turbines at other sites have been found to kill bats, said Rick Lambert, a member of the Virginia Highlands Grotto of the National Speleological Society and local bat enthusiast.
At the Mountaineer Wind Energy Center in West Virginia, 47.5 bats were killed per turbine annually, he said.
In addition to common bats, there are 41 Indiana Bat caves within 50 miles and 23 Virginia Big-eared Bat caves within 30 miles of the proposed wind farm, Lambert said. Both species of bats are endangered and the turbines will be well within their migratory distance, he said.
Also filed under [
Impact on Landscape|
Impact on People]
Turbines Must Deal With The Birds And The Bats
January 25, 2008 by Hannah Northey in Daily News Record
January 25, 2008 by Hannah Northey in Daily News Record
The environmental impact of Virginia's first wind farm in Highland County could shed light on how successful such farms will be in the Valley, state officials say.
State agencies, led by the Virginia Department of Game and Inland Fisheries, will monitor the Highland New Wind Development LLC's 20 wind turbines to see how federally protected bats and birds are affected.
Biologists are concerned that inland wind farms on the East Coast could kill large numbers of common bats, and possibly affect the federally protected Indiana bat and Virginia big-eared bat, according to the State Corporation Commission.
The commission approved the Highland County project this week but required the developers to study its impact on the animals.
"We still have no experience in Virginia," said Ken Schrad, an SCC spokesman. "The Highland project, with its monitoring and mitigation program, will provide that experience for future projects."
Also filed under [
Impact on Birds|
Impact on Bats]
State approves wind plant permit; Residents, supervisors consider next moves
January 3, 2008 by Anne Adams in The Recorder
January 3, 2008 by Anne Adams in The Recorder
HNWD attorneys Brian Brake and John Flora declined to make any comment on the SCC's decision or answer questions about how the company will proceed from here.
At this point, Bailey said he doubted the SCC would reconsider its permit order. "Legal arguments at the SCC are always edgy, and here, it's so clear how seriously they have taken the environment. The chances (of an appeal) prevailing are remote ... This has set a wonderful precedent for Virginia, and I can't see wind turbines exploding in this state now."
And, before construction can begin, HNWD is required to submit a final site plan. The company cannot do anything, including storing equipment on site, until that site plan is approved. Before HNWD can get a county building permit, it must also file a performance bond. For the first partial year and five subsequent years, that bond must be for $2,500 per turbine tower; for the remaining years, the amount is $6,000 each.
Also filed under [
Impact on Views|
Impact on People]
Power In The Breeze; McBride Seeks Funding For Wind Energy Project
December 27, 2007 by Dan Wright in The Daily News Record
December 27, 2007 by Dan Wright in The Daily News Record
Last week, the State Corporation Commission granted conditional approval for the company to build up to 20 turbines, each about 400 feet tall, on Red Oak Knob and Tamarack Ridge near the West Virginia border. ...McBride's project faced considerable opposition from environmentalists.
It was widespread among residents who see Highland County as a pristine rural area and "a sort of last frontier," Sullenberger said.
The Virginia Department of Game and Inland Fisheries summarized the opposition in a September 2006 letter to the SCC.
"We support the use of alternative energy sources, including wind energy" the DGIF said. "However, we feel this project presents an unacceptable risk to wildlife."
Also filed under [
General|
Zoning/Planning]
Highland New Wind chose not to seek a federal permit to protect the wind farm from possible immediate shutdown by government order if an endangered or threatened animal is killed or injured. That's a risk that regulators said the company is free to take if it wishes.
Another battleground was how much Highland New Wind will pay for wildlife measures. Thursday's ruling initially capped monitoring costs at up to $150,000 a year. It capped shutdown-related expenses to benefit wildlife at either $50,000 a year or 0.85 percent of revenue from the prior year, whichever is higher.
Previously released case documents said the project is expected to generate lots of cash long-term. Company financial analysts predicted Highland New Wind could earn an annual profit of $4.2 million after major expenses are paid off in 10 to 15 years. With state approval now in hand, the company said it will begin recruiting investors.
The first wind-powered electric generation project in Virginia will be permitted on the remote ridges of Highland County, the State Corporation Commission said Thursday.
The commission granted conditional approval to Highland New Wind Development's $60 million proposal to place 19 turbines more than 400 feet tall on a 4,400-foot ridge near the West Virginia border.
The company must spend up to $150,000 a year to monitor and mitigate harm to birds and bats that could be caused by the whirling turbine blades, the SCC said. Environmentalists have contended many endangered species would be threatened by the project, and an SCC hearing examiner concluded that the turbines were a "significant risk" to bats and "a lesser risk" to birds.
Also filed under [
Impact on People|
Zoning/Planning]
Wind farm may have to monitor bird and bat kills; An SCC officer said wildlife protection outweighs financial concerns
October 18, 2007 by Jeff Sturgeon in Roanoke Times
October 18, 2007 by Jeff Sturgeon in Roanoke Times
Backers of a proposed wind farm in Highland County would have to search daily for dead birds and bats and curtail turbine operations to limit loss of animal life under a proposed wildlife-protection plan issued Wednesday by a Virginia State Corporation Commission hearing officer. ...Citing "significant risk" to bats, and "a lesser risk" to birds, Skirpan recommended that backers of the 19-turbine project should pay for monitoring and altering their use, including speed, for the life of the wind farm.
SCC official recommends monitoring wind energy project for its lifespan
October 18, 2007 by Anne Adams in The Recorder
October 18, 2007 by Anne Adams in The Recorder
Following State Corporation Commission's decision in March to remand the case to its hearing examiner for further review on environmental concerns, months of testimony have been submitted and reviewed.
This week, the hearing examiner, Alexander J. Skirpan, submitted another report to commissioners, this time recommending "robust" monitoring of the potentially adverse impacts to wildlife, for the expected 20-year life of the project. ...Skirpan had previously concluded HNWD's project be approved by the SCC. But commissioners wanted to know what kind of details a monitoring and mitigation plan would include, rather than leaving those issues up to the Virginia Department of Game and Inland Fisheries, and HNWD.
Turbulence over turbines at Virginia's first planned wind farm
September 16, 2007 by Scott Harper in The Virginia Pilot
September 16, 2007 by Scott Harper in The Virginia Pilot
The ferocity of local opinions against the project has raised questions about Virginia's future as a wind-energy producer, with surrounding counties unsure about opening their mountaintops to investors, too.
The debate also comes as entrepreneurs in other states are rushing to erect turbines, take advantage of federal tax credits and create electricity without the emissions linked to global warming.
Wind Project Developer Seeks to Avoid Wildlife Protection Measures
July 16, 2007 by VaWind Press Release
July 16, 2007 by VaWind Press Release
Highland New Wind is testifying that it cannot afford the wildlife protections recommended by wildlife agencies, conservation groups, and citizen respondents in the case.
Despite the prospects of government incentives, which would cover the majority of development costs, it remains a marginal project, promising negligible benefits and huge environmental costs.
Also filed under [
General|
Zoning/Planning]
MONTEREY - Preparations have been under way for weeks, and this Tuesday, the State Corporation Commission will hold its second evidentiary hearing on what could be Virginia's first industrial wind energy utility.
After months of testimony, the SCC did not reach a decision on whether to grant Highland New Wind Development a state permit to build its facility here atop Allegheny Mountain. Instead, the three commissioners remanded the case back to the SCC hearing examiner with instructions to gather more information, particularly on how to prevent or reduce the 39-megawatt plant's impacts on the environment, and monitor those after construction.
HNWD is expected to call some of the same people it did at the first hearing to rebut testimony of expert witnesses who have spoken on behalf of The Nature Conservancy and Highland citizens opposed to the project.
Also filed under [
General|
Zoning/Planning]
SCC orders bird, bat protection near proposed wind farm
April 6, 2007 by Associated Press in Daily Press
April 6, 2007 by Associated Press in Daily Press
The State Corporation Commission on Friday sent a proposal for Virginia's first utility-grade wind farm back to a hearing examiner for development of a plan to mitigate harm to rare birds and bats on Highland County ridges.
In recommending approval last month for construction of 19 turbines, SCC hearing examiner Alexander Skirpan found that the Highland New Wind Development proposal posed a risk to birds and bats. Skirpan recommended a monitoring program, developed by the company and the Virginia Department of Game and Inland Fisheries, to reduce the environmental hazard.
The giant wind farm of 19 electricity-generating windmills in Highland County recently approved by the State Corporation Commission wasn't on the game department's radar. Studies elsewhere have shown that the 400-foot-high wind turbines kill bats and migrating songbirds and raptors.
By the time the SCC asked the game department to review the proposal, Zadnik said, the developer had already gotten permission from the county to build.
Also filed under [
Topics]
ROANOKE -- A state hearing examiner has recommended construction of the first utility-grade wind farm in Virginia, provided it meets conditions to minimize harm to the environment.
The recommendation announced Thursday goes to the State Corporation Commission, which will decide whether to approve construction of the 19-turbine development on Highland County ridges.
SCC hearing examiner Alexander Skirpan found that the project by Highland New Wind Development poses a risk to bats and birds, but said a monitoring program by the company and a state agency following construction would help reduce the hazard.
Endangered bats and birds are at risk from Virginia's first proposed wind farm, but construction should proceed with the warning that its massive blades will be stopped at times if too many carcasses pile up.
That was the decision Thursday from a State Corporation Commission hearing examiner who gave conditional approval to the controversial project in Highland County.
Supporters and opponents have 21 days to comment on the hearing examiner's report. The case will then be forwarded to the commission for a final decision, which is expected early this summer.