Jack Mountain project delayed; Wind developer failed to give notice; vote put off until June
Those headed to West Virginia’s capital city this week for hearings on the Liberty Gap wind utility proposal came home early.
The state’s Public Service Commission was set to begin evidentiary hearings Tuesday morning on Liberty Gap LLC’s request for a permit to build a 50-megawatt wind energy facility on Jack Mountain in Pendleton County.
But at the last minute, the company realized it had not published public notices about the hearings as required by the PSC.
When it realized the error, Liberty Gap asked the PSC to postpone the hearings 30 days, and move the statutory deadline for the PSC’s final decision back 30 days as well.
The PSC denied that motion, and cancelled the evidentiary portion of the hearings, though it did receive limited public comment on the project Tuesday, and agreed to hear argument from all parties involved about how to proceed.
December 14, 2006
by Anne Adams, Staff Writer
in The Recorder
Those headed to West Virginia’s capital city this week for hearings on the Liberty Gap wind utility proposal came home early.
The state’s Public Service Commission was set to begin evidentiary hearings Tuesday morning on Liberty Gap LLC’s request for a permit to build a 50-megawatt wind energy facility on Jack Mountain in Pendleton County.
But at the last minute, the company realized it had not published public notices about the hearings as required by the PSC.
When it realized the error, Liberty Gap asked the PSC to postpone the hearings 30 days, and move the statutory deadline for the... [continue via Web link]