Wind turbine project gets extension
Construction on more than a dozen wind turbines has not started in Cattaraugus County due to a lack of federal dollars and a lawsuit by residents. The town of Allegany is giving the company some time to sort out the problems.
June 11, 2012
by Katie Cummings
in YNN
ALLEGANY, N.Y. - The Town of Allegany planning board approved an extension Monday on a special use permit for Ever Power Wind Holdings.
The New York City based company wants to build 29 wind turbines in the town. They were slated to start construction at the end of 2011, but a non-renewal in federal tax credits, along with a lawsuit by the Concerned Citizens of Cattaraugus County, has prevented that.
"They would be able to buy people out or get an easement, noise easement from people within 2,500 feet. The people at 2,500 and one would get excessive noise and would... [continue via Web link]