Morrow County wind farm moving forward
"We have to admit we've not seen the success we had hoped," said Nazre G. Adum, director of business development for Invenergy.
The company has leased options on about 6,000 of the 15,000 acres it needs to bring the project online. Adum said he was optimistic the company would secure the rest of the options within the next year.
August 11, 2010
by David Kennard
in News Journal
MOUNT GILEAD -- Company representatives say they are committed to a 120-turbine wind farm near Mount Gilead even though they have only about half the acreage they need to move forward.
About 100 landowners attended a dinner Tuesday night to hear an update and ask questions about the project.
"We have to admit we've not seen the success we had hoped," said Nazre G. Adum, director of business development for Invenergy.
The company has leased options on about 6,000 of the 15,000 acres it needs to bring the project online. Adum said he was optimistic the company would secure the rest of the... [continue via Web link]