News
Cohocton to receive $635,000 for roads as part of settlement with First Wind
After a month of negotiation, Cohocton town officials are expecting a settlement with wind developer First Wind to the tune of $635,000.
The Cohocton town board gave a tentative OK to the agreement to fix up town roads damaged by construction equipment at Monday night's board meeting, but there are a few minor issues left to iron out, said town Supervisor Jack Zigenfus.
June 16, 2009
by Bob Clark
in Evening Tribune
Atlanta, N.Y. -- After a month of negotiation, Cohocton town officials are expecting a settlement with wind developer First Wind to the tune of $635,000.
The Cohocton town board gave a tentative OK to the agreement to fix up town roads damaged by construction equipment at Monday night's board meeting, but there are a few minor issues left to iron out, said town Supervisor Jack Zigenfus.
"There's only a couple little things remaining to be ironed out," Zigenfus said. "Kind of ‘what if, down-the-road' things."
In the agreement, First Wind will pay the town $335,000 within 10 days of approval. The agreement also... [continue via Web link]