County judge denies wind farm appeal; Enxco will go to state for project approval
Kittitas County Superior Court Judge Michael Cooper on Friday ruled that county commissioners acted legally and within their authority to deny approval of the Desert Claim Wind Power Project earlier this year.
November 8, 2005
by Mike Johnston
in Daily Record
Kittitas County Superior Court Judge Michael Cooper on Friday ruled that county commissioners acted legally and within their authority to deny approval of the Desert Claim Wind Power Project earlier this year.
County commissioners on April 5 denied permits requested by EnXco USA Inc. for the French-based company’s planned 120-turbine wind farm eight miles north of Ellensburg. The company later filed an appeal in county Superior Court. A hearing on the appeal took place Oct. 6.
EnXco officials this morning said they were disappointed in the judge’s ruling. They said they intend to seek approval of the... [continue via Web link]
County commissioners on April 5 denied permits requested by EnXco USA Inc. for the French-based company’s planned 120-turbine wind farm eight miles north of Ellensburg. The company later filed an appeal in county Superior Court. A hearing on the appeal took place Oct. 6.
EnXco officials this morning said they were disappointed in the judge’s ruling. They said they intend to seek approval of the... [continue via Web link]