Crystal Lake wind farm waiting on permit approvals
Land acquisition for the 100-turbine wind farm proposed by Crystal Lake is complete but the project still must jump through some regulatory hoops before construction can begin. Steve Stengel, director of corporate communications for FPL Energy, said the company is waiting to hear about a request for utility permits for overhead and underground utility lines in Hancock County.
November 9, 2007
by Peggy Senzarino
in Globe Gazette
CRYSTAL LAKE - Land acquisition for the 100-turbine wind farm proposed by Crystal Lake is complete but the project still must jump through some regulatory hoops before construction can begin.
Steve Stengel, director of corporate communications for FPL Energy, said the company is waiting to hear about a request for utility permits for overhead and underground utility lines in Hancock County.
FPL Energy is an affiliate of Juno Beach, Fla.-based Florida Power & Light Co.
The company wants to install transmission lines to bring power from the wind farm to the Lime Creek Power Station, which is located south of Manly.
The Hancock County... [continue via Web link]