Memo from the Massachusetts Department of Public Utilities Chairman, Paul Hibbard, to the ISO New England. Chairman Hibbard expresses his concerns over the push to regionalize costs for building expensive transmission lines to service renewable projects (wind) built far from load centers. Current FERC rules are unclear on how to justify distribution of the costs across all ratepayers within the region unless it can be shown such transmission is needed to ensure the reliability and integrity of the grid.
Lempster Mountain Wind Power Project: Direct Pre-filed Testimony of Lisa Linowes
February 7, 2007
by Lisa Linowes
Why did you petition to become an intervenor in this matter before the NH SEC?
With New Hampshire’s recent reinstatement of PILOT agreements and legislative efforts to a Renewable Portfolio Standard, the regulatory groundwork is being laid for more wind facilities to enter the state. Yet, New Hampshire, like many states, has no consistent regulatory process in place for reviewing these projects to ensure our environmental, societal, and economic interests are protected. The work the NH SEC has agreed to undertake in reviewing this application is precedent setting. How the committee approaches its review and the weight it places on arguments presented by all sides will impact other developments in the State as pertains to renewable energy projects.
There are a multitude of conflicting issues at play when considering any wind project. My commitment to this process is to help provide, to the best of my ability, valuable and timely information that will assist the Committee in making an informed decision on this application.
Also filed under [
General|
Impact on Wildlife|
Impact on Birds|
Impact on Landscape|
Pollution|
Impact on Space]
The Challenge of Energy Policy in New England
April, 2006
by Carrie Conaway, The New England Public Policy Center at Federal Reserve Bank of Boston
Renewable energy sources have disadvantages as well as advantages, however.
Although their costs have decreased in
recent years, many renewables are still more
costly than traditional sources. Some are also
available only intermittently; for example,
wind can be variable and hydroelectric is seasonal. And while many people are in favor of
renewables in principle, many are also
unhappy when faced with the prospect of a
windmill or a trash-burning power plant in
their neighborhood. These facilities face the
same siting and investment difficulties that
any electrical facility would, as the developers of a proposed wind farm off the coast of
Cape Cod have discovered in recent years.
...the MEA Report can be used to estimate the value (avoided emissions) of Renewable Energy Certificates (REC) by providing both REC suppliers and stakeholders with information that can be used to communicate the environmental benefits of RECs and works to enhance the overall REC marketplace.
Editor's Note: As noted below under Methodology [emphasis added], this report appears to substantiate the point that wind energy would not backdown "baseload" generation.
Editor's Note: As noted below under Methodology [emphasis added], this report appears to substantiate the point that wind energy would not backdown "baseload" generation.
Also filed under [
General|
Pollution|
Tax Breaks & Subsidies|
Connecticut|
Massachusetts|
Maine|
Rhode Island|
Vermont]
This presentation indicates that for New England the increasing demand for
summer-time electricity is greater and increasing faster than
winter-time demand. The fast-rising need for power in summer will
likely result in construction of new power plants to keep ahead of
demand - although inland industrial wind plants will not be able to contribute much
to this demand period due to their very low capacity factor during
summer months.
Comments to FERC by the New England Conference of Public Utility Commissions and the Vermont Department of Public Service