Structural Failure
One of the three 60-foot-tall wind turbines at the edge of the Perkins High School student parking lot lays on the ground. The pole was removed from the 4-foot deep, 60-ton concrete base. ..."We have no updates," he said. "The manufacturer is finalizing the investigation as to the malfunction of the blades."
Part of wind turbine breaks and lands in open field
February 21, 2009 by Danielle Wagner in KWWL TV 7
February 21, 2009 by Danielle Wagner in KWWL TV 7
Part of a wind turbine under construction broke apart Saturday morning.
The problem started Friday when construction crews were installing a second wind turbine for Waverly Light and Power.
During the process, a construction error caused the rotor and blades to start moving in the wind prematurely - spinning uncontrollably and unable to stop until it broke.
An unexpected problem has occurred with construction of second wind turbine
February 20, 2009 by Waverly Light and Power
February 20, 2009 by Waverly Light and Power
The construction company, ICS of North Dakota, lifted the wind turbine rotor assembly, to which the blades attach, 246 feet high into place late yesterday afternoon. After it was lifted it was discovered the blades were not ‘feathered' or turned properly so they could not catch the wind. In the position the blades are in, the wind caught the blades causing them to spin.
When this was discovered, the Bremer county sheriff's department was notified and all personnel were evacuated, including two homeowners who were outside of the recommended danger zone.
Bill Fish wants the Municipality of Chatham-Kent to investigate homemade windmills after his neighbour's device came crashing through his roof during yesterday's high winds.
He was shocked awake around 3 a.m. when an eight-foot-long wooden blade penetrated the roof, before piercing through the ceiling and wall in a sewing room of his Dufferin Avenue home, located outside of Wallaceburg in Chatham Township.
Also filed under [
Ohio]
3 turbines crash after blades from one break
February 10, 2009 by Richard Payerchin in Morning Journal
February 10, 2009 by Richard Payerchin in Morning Journal
Three wind turbines at Perkins High School crashed Saturday when the blades broke off one of them.
No one was hurt when parts of the fiberglass blades came off the turbine as it spun, winging the blades up to 40 yards away from the silver monopole tower, near the high school at 3714 Campbell St.
The remaining two turbines will not be used until they are inspected and officials figure out what caused the blades to break.
UFO wind turbine 'broke due to mechanical failure not collision with flying object'
February 10, 2009 by Matthew Moore in Telegraph.co.uk
February 10, 2009 by Matthew Moore in Telegraph.co.uk
A 65 ft blade that flew off the turbine came loose after bolts attaching it to the hub failed, not because of a collision, examination of the components has revealed. ..."The bolt failure was the effect not the cause of the problem. They have ruled out bolt fatigue and design problems, and we know that they were properly put on," said Dale Vince the co-founder of Ecotricity, which owns the farm.
A wind turbine at Perkins High School fell apart Saturday. ...He looked next door, where the three wind turbines at Perkins High School were spinning in Saturday's high winds, to see part of a turbine blade fly off and land in the student parking lot.
A wind farm turbine caught fire at the Cathedral Rocks Wind Farm in the early hours of Tuesday morning. ...The company said yesterday it expects the damage bill to be about $2 million, but it would determine an exact amount when it finishes its investigation.
Also filed under [
Safety|
Australia / New Zealand]
A $6 million wind turbine has caught fire near Port Lincoln, starting blazes on the ground as embers fall.
The fire, at the Cathedral Rocks Wind Farm about 30km southwest of the town, was first noticed by a boat about 1am.
Also filed under [
Safety|
Australia / New Zealand]
Damaged rotor blades and forex losses caused the world's fifth-largest wind turbine maker Suzlon Energy post a consolidated net loss of Rs 34.90 crore for the quarter ended December 2008 against a Rs 142.8 crore profit in the corresponding previous quarter. ...Cracks were detected in 170 of the 1,250 blades for 400 turbines of the S88 V2 model supplied by Suzlon in 2007 to two of its major clients in the US -- Edison International and John Deere.
Also filed under [
Impact on Economy|
Asia]
U.S. Forest Service officials had a tour scheduled Wednesday afternoon to show off to journalists a pair of recently installed wind turbines.
But they had to cancel the tour when 100 mph winds damaged one of the turbines Tuesday night.
"We were kind of tickled" by the irony, acknowledged Maribeth Pecotte, a spokeswoman in the Forest Service's Boulder Ranger District office. ...The turbine project is costing the Forest Service $171,568 over a 15-year financing contract, Pecotte said.
Also filed under [
Colorado]
Windmill repair update; A city investigation continues
January 29, 2009 by Jackie Devereaux in Desert Valley Star
January 29, 2009 by Jackie Devereaux in Desert Valley Star
City officials continue to investigate and keep tabs on how a Florida power company is meeting requirements for repairing their damaged and malfunctioning windmills here. ...FPL/NER owns and operates approximately 60 wind turbines in question. It's astonishing that there is a reported 40 percent that are malfunctioning, in disrepair, or need maintenance.
Also filed under [
Safety|
California]
Work to get the wrecked 'UFO' wind turbine up and running at Conisholme wind farm is underway.
Despite the explanation as to why one of the baldes 'fell' and another was left bent still being unknown, workers are at the site and in the next few days, all three 65ft blades and the central hub will be replaced.
Ecotricity, which owns the site, are continuing investigations and have said they are not ruling anything out - though the extent of damage was "unique".
To make one of these blades fall off, or to bend it, takes a lot Dale Vince, Ecotricity.
Call for Conisholme wind farm to be closed; Ecotricity say there is no danger to the public
January 7, 2009 in Louth Leader
January 7, 2009 in Louth Leader
A call has been made for the Conisholme wind farm to be closed - before someone is injured.
Coun Robert Palmer, Chairman of East Lindsey District Council, says the site should be closed off to the public while an independent health and safety investigation is carried out.
On Sunday morning local people woke to find a blade on one of the 89 metre high wind turbines in Fen Lane had broken off.
Has the tenacle UFO got something to do with the broken blades at Conisholme?
Engineers from Ecotricity are working to establish how a 20m blade mysteriously fell off a turbine at Conisholme wind farm - but residents have their own conclusions.
It is believed the a blade fell off the 89m turbine and another was left badly bent on Sunday January 4.
Over the weekend, reports of a blade missing from one of the mammoth turbines and another blade being badly bent out of shape came to light.
The cause of the damage has yet to be established, however some say it could be down to icy weather.
Also filed under [
UK]
An investigation suggests an explosion and fire inside a Nebraska wind turbine was caused by a "foreign object". ...the "object" blew into the turbine causing the blast.
One of the blades of a Suez Energy North America V-90 wind turbine situated approximately 1,600 feet away, between her house and the Northumberland Strait, was damaged. Pieces were dangling from the blade and other pieces were strewn throughout a field, right up to her back door. ...Sabota reported that blades on two of the three turbines in Suez Renewable Energy North America's Norway wind park sustained some damage.